17324 W CHASE ST 91325

Certificate Information: 17324 W CHASE ST 91325

Application / Permit
22010-20000-03801
Plan Check / Job No.
B22VN11662
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW DETACHED SINGLE FAMILY DWELLING PER SB9; EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/23/2023
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/26/2022 SELLA BENYAMIN
Corrections Issued 8/29/2022 SELLA BENYAMIN
Quality Review Completed 9/1/2022 STEVEN KIM
Plan Check Approved 5/23/2023 SELLA BENYAMIN
Issued 5/23/2023 APPLICANT
CofO in Progress 8/1/2024 JAVIER RAMOS JR
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/15/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 4/3/2023 KURT CORRAL
Sewer availability Cleared 4/3/2023 MEGAN GODINEZ
Senate Bill 9 Cleared 4/4/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 4/10/2023 CARLOS AGUILERA
Low Impact Development Cleared 4/21/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/21/2023 MARKOS PEREZ-BRAN

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: NA35492       ,
Contractor Owner-Builder       ,
Engineer Van, Elden, Alexander Craig; Lic. No.: C71696 2415 FORDHAM DR      COSTA MESA, CA 92626

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/13/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/23/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/2/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 4/2/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Approved JAVIER RAMOS JR
Green Building Rough 4/2/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/2/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/2/2024 Approved JAVIER RAMOS JR
Insulation 4/9/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/9/2024 Approved MATTHEW NELSON
Shower Pan 4/9/2024 Approved MATTHEW NELSON
Drywall Nailing 4/15/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 4/15/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/5/2024 Partial Approval JAVIER RAMOS JR
Sewer 6/5/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/2/2024 Approved KEVIN BERBERYAN
Final 7/2/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 7/2/2024 Approved KEVIN BERBERYAN
Green Building Final 7/2/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 7/2/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 7/2/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 7/10/2024 Approved JAVIER RAMOS JR
Final 7/10/2024 Partial Inspection JAVIER RAMOS JR
Green Building Final 7/10/2024 Approved JAVIER RAMOS JR
HVAC-Final 7/10/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 7/10/2024 Approved JAVIER RAMOS JR
Final 8/1/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 8/1/2024 Approved JAVIER RAMOS JR