13023 W ARMINTA ST 91605
Certificate Information: 13023 W ARMINTA ST 91605
- Application / Permit
- 22010-20000-03773
- Plan Check / Job No.
- B22VN11582
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22' X 24'-3" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/23/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Plan Check Approved | 4/13/2023 | SELLA BENYAMIN |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 3/21/2025 | VINCENT HANLEY |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/12/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/12/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 10/24/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/22/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/2/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/27/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/8/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 1/8/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/18/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/18/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 1/18/2024 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 1/18/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/29/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 1/29/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 2/20/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 2/20/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 2/26/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/26/2024 | Approved | GREGG CUMMINGS |
| Insulation | 2/26/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 3/5/2024 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 3/13/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/28/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 4/29/2024 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 4/29/2024 | Approved | GREGG CUMMINGS |
| Sewer | 5/3/2024 | Approved | DAVID MATSON |
| Final | 8/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Not Required | GREGG CUMMINGS |
| Service/Power Release | 8/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/7/2024 | Approved | GREGG CUMMINGS |
| Final | 12/17/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/17/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 12/17/2024 | Approved | VINCENT HANLEY |
| Final | 2/4/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 3/20/2025 | Approved | VINCENT HANLEY |
| Final | 3/20/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/20/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/20/2025 | Approved | VINCENT HANLEY |