5927-5929 N MELVIN AVE 91356

Certificate Information: 5927-5929 N MELVIN AVE 91356

Application / Permit
22010-20000-03767
Plan Check / Job No.
B22VN11561
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY DWELLING EXCEPT 7'6" LF AT NORTH EAST PORTION OF THE LOT AND BUILD AN IRREGULAR 76' X 51'6" TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED TWO CAR GARAGE AND WITH ATTACHED ACCESSORY DWELLING UNIT AS PER CA GOVT CODE 65852.2 (E)(1)(A), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 RARES BODEA
Corrections Issued 8/15/2022 RARES BODEA
Quality Review Completed 8/18/2022 STEVEN KIM
Building Plans Picked Up 9/14/2022 APPLICANT
Applicant returned to address corrections 1/17/2023 RARES BODEA
Applicant returned to address corrections 6/22/2023 RARES BODEA
Plan Check Approved 7/12/2023 RARES BODEA
Issued 7/12/2023 APPLICANT
CofO in Progress 2/4/2025 JON MCHUGH
CofO in Progress 4/28/2025 JON MCHUGH
Permit Finaled 5/2/2025 JOHN JANSON
CofO Issued 5/2/2025 JOHN JANSON
Permit Finaled 5/2/2025 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 11/28/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/29/2022 COLIN LOREDO
Sewer availability Cleared 12/1/2022 COLIN LOREDO
Tract Map conditions Cleared 12/12/2022 NELSON RODRIGUEZ
Tract Map conditions Cleared 12/12/2022 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 12/13/2022 KURT CORRAL
Low Impact Development Cleared 12/20/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 12/22/2022 MEGAN GODINEZ
Trees in Parkway Cleared 1/5/2023 ADALBERTO VERA
Address approval Cleared 7/12/2023 MARKOS PEREZ-BRAN
Hold Cleared 8/21/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/24/2023 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 10/24/2023 Corrections Issued JON MCHUGH
Green Building Rough 10/24/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 10/24/2023 Not Ready for Inspection JON MCHUGH
Special/Order Compliance 10/24/2023 Not Ready for Inspection JON MCHUGH
Underground Mechanical 10/24/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 10/30/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval MORRIS JACKSON
Special/Order Compliance 12/21/2023 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Approved JEFFREY PARD
Special/Order Compliance 12/22/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 1/12/2024 Partial Approval JON MCHUGH
HVAC-Rough 2/7/2024 Approved JON MCHUGH
PLUMBING-Rough 2/7/2024 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 2/13/2024 Corrections Issued JON MCHUGH
Green Building Rough 2/13/2024 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 2/13/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 2/14/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 3/1/2024 Approved JON MCHUGH
Insulation 3/1/2024 Approved JON MCHUGH
Interior/Exterior Lathing 3/1/2024 Approved JON MCHUGH
Shower Pan 3/1/2024 Approved JON MCHUGH
Drywall Nailing 3/8/2024 Approved VINCENT HANLEY
Final 1/3/2025 Corrections Issued JON MCHUGH
Green Building Final 1/3/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 1/3/2025 Not Ready for Inspection JON MCHUGH
Smoke Detectors 1/3/2025 Approved JON MCHUGH
Final 1/14/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 1/14/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 2/3/2025 Approved JON MCHUGH
Final 2/3/2025 OK to Issue CofO JON MCHUGH
HVAC-Final 2/3/2025 Approved JON MCHUGH
PLUMBING-Final 2/3/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved JON MCHUGH
Service/Power Release 2/3/2025 Approved JON MCHUGH
Final 4/28/2025 OK to Issue CofO JON MCHUGH