8821 N DEBRA AVE 91343

Certificate Information: 8821 N DEBRA AVE 91343

Application / Permit
22010-20000-03765
Plan Check / Job No.
B22VN11554
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40'-0" X 31'-9" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 10/11/2022
Issuing Office
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/1/2022 ARTIN ZARUKIAN
Corrections Issued 8/1/2022 ARTIN ZARUKIAN
Building Plans Picked Up 8/3/2022 APPLICANT
Applicant returned to address corrections 10/11/2022 JEROME MAGAT PALMA
Plan Check Approved 10/11/2022 JEROME MAGAT PALMA
Issued 10/11/2022 APPLICANT
CofO in Progress 5/11/2023 MATTHEW NELSON
Permit Finaled 5/23/2023 MICHAEL SMITH
CofO Issued 5/23/2023 MICHAEL SMITH
Permit Finaled 5/23/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/4/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/8/2022 MEGAN GODINEZ
Sewer availability Cleared 8/8/2022 MEGAN GODINEZ
Construction near power lines Cleared 9/14/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/11/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 10/11/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2022 Partial Approval RAUL OLAGI
Sewer 11/3/2022 Approved RAUL OLAGI
Underground Mechanical 11/3/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 11/9/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/10/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 2/10/2023 Approved RAUL OLAGI
Green Building Rough 2/10/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 2/10/2023 Approved RAUL OLAGI
PLUMBING-Rough 2/10/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 2/10/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/22/2023 Partial Approval WILLIAM WREN
Insulation 3/2/2023 Approved RAUL OLAGI
Shower Pan 3/2/2023 Approved RAUL OLAGI
Drywall Nailing 3/8/2023 Approved RAUL OLAGI
Green Building Rough 3/8/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 3/8/2023 Approved RAUL OLAGI
ELECTRICAL-Final 5/2/2023 Approved RAUL OLAGI
Final 5/2/2023 Corrections Issued RAUL OLAGI
Green Building Final 5/2/2023 Approved RAUL OLAGI
HVAC-Final 5/2/2023 Approved RAUL OLAGI
PLUMBING-Final 5/2/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 5/2/2023 Approved RAUL OLAGI
Final 5/10/2023 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved MATTHEW NELSON
Service/Power Release 5/10/2023 Approved MATTHEW NELSON