16939 W MARLIN PL 91406

Certificate Information: 16939 W MARLIN PL 91406

Application / Permit
22010-20000-03751
Plan Check / Job No.
B22VN11545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New Detached 600 SF ADU per state law 29'X21'-6" all work done per wfpp
Permit Issued
Issued on 2/5/2023
Issuing Office
Current Status
CofO Issued on 8/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 JOE VO
Corrections Issued 8/7/2022 JOE VO
Plan Check Approved 1/5/2023 KHUONG TRUONG
Issued 2/5/2023 APPLICANT
CofO in Progress 6/28/2024 JON MCHUGH
Permit Finaled 8/16/2024 JOHN JANSON
CofO Issued 8/16/2024 JOHN JANSON
Permit Finaled 8/16/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/17/2022 CARLOS AGUILERA
Sewer availability Cleared 10/17/2022 CARLOS AGUILERA
Low Impact Development Cleared 12/9/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 1/3/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2023 Corrections Issued JON MCHUGH
Underground Mechanical 2/15/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 3/8/2023 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 3/9/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval JON MCHUGH
Green Building Rough 3/24/2023 Not Ready for Inspection JON MCHUGH
Wood Frame 3/24/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 4/5/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Approved JON MCHUGH
Green Building Rough 4/5/2023 Approved JON MCHUGH
Interior/Exterior Lathing 4/5/2023 Partial Approval JON MCHUGH
Verify Sprinkler Sign Off 4/5/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 7/13/2023 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 7/13/2023 Corrections Issued JON MCHUGH
PLUMBING-Rough 7/13/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 8/1/2023 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 8/1/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 8/1/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 8/21/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 8/21/2023 Approved JON MCHUGH
HVAC-Rough 8/21/2023 Corrections Issued JON MCHUGH
Insulation 8/21/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 8/30/2023 Partial Approval JON MCHUGH
HVAC-Rough 8/30/2023 Approved JON MCHUGH
Insulation 8/30/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 9/15/2023 Approved JEFFREY PARD
Insulation 9/15/2023 Approved JEFFREY PARD
Drywall Nailing 9/28/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/3/2023 Not Ready for Inspection JON MCHUGH
Final 2/15/2024 Corrections Issued JON MCHUGH
Green Building Final 2/15/2024 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready JON MCHUGH
Service/Power Release 2/15/2024 Not Ready for Inspection JON MCHUGH
Smoke Detectors 2/15/2024 Not Ready for Inspection JON MCHUGH
Final 4/24/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 4/24/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 4/24/2024 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 4/24/2024 Approved ARUTYUN MADATYAN
Final 6/28/2024 OK to Issue CofO JON MCHUGH
Green Building Final 6/28/2024 Approved JON MCHUGH
Service/Power Release 6/28/2024 Approved JON MCHUGH