845 E 87TH PL 90002
Certificate Information: 845 E 87TH PL 90002
- Application / Permit
- 22010-20000-03742
- Plan Check / Job No.
- B22VN11528
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan; New 899 sf detached ADU w/ 66 sf covered porch ( per LAMC 12.22 A.33(c) and (d) ) "Comply with Department Order effective date 06/10/2019"
- Permit Issued
- Issued on 3/31/2023
- Issuing Office
- Current Status
- CofO in Progress on 5/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 8/31/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 9/2/2022 | OMID HEDAYAT |
| Plan Check Approved | 3/21/2023 | MOHAMMAD ESMAILI |
| Issued | 3/31/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | GABRIEL HERRERA |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/16/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 12/29/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: NA76510 | , |
Inspector Information
| EDMUND LUM, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUCIANO GAUNA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAIME RIOS, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDEY CHAPARRO, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN BARNES, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| PATRICK LIEBREGT, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GLEN RAND, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAWN ESHBACH, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
| GABRIEL HERRERA, (213) 252-3962 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/19/2023 | Approved | NEVILLE REID |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Corrections Issued | GABRIEL HERRERA |
| Deputy Drilled-In Anchors | 5/3/2023 | Approved | GABRIEL HERRERA |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Approved | GABRIEL HERRERA |
| Footing/Foundation/Slab | 5/4/2023 | Approved | GABRIEL HERRERA |
| BUILDING-Rough-Frame | 6/14/2023 | Corrections Issued | GABRIEL HERRERA |
| Green Building Rough | 6/14/2023 | Not Ready for Inspection | GABRIEL HERRERA |
| Verify Sprinkler Sign Off | 6/14/2023 | Not Ready for Inspection | GABRIEL HERRERA |
| ELECTRICAL-Rough | 7/27/2023 | Approved | NEVILLE REID |
| HVAC-Rough | 7/27/2023 | Approved | NEVILLE REID |
| Interior/Exterior Lathing | 7/27/2023 | Approved | NEVILLE REID |
| PLUMBING-Rough | 7/27/2023 | Approved | NEVILLE REID |
| Sewer | 7/27/2023 | Approved | NEVILLE REID |
| Insulation | 8/7/2023 | Approved | NEVILLE REID |
| Drywall Nailing | 8/14/2023 | Approved | NEVILLE REID |
| Shower Pan | 8/14/2023 | Approved | NEVILLE REID |
| ELECTRICAL-Final | 2/28/2024 | Approved | GABRIEL HERRERA |
| PLUMBING-Final | 2/28/2024 | Approved | GABRIEL HERRERA |
| Service/Power Release | 2/28/2024 | Approved | GABRIEL HERRERA |
| BUILDING-Rough-Frame | 3/6/2024 | Corrections Issued | GABRIEL HERRERA |
| Final | 3/6/2024 | Corrections Issued | GABRIEL HERRERA |
| Green Building Final | 3/6/2024 | Corrections Issued | GABRIEL HERRERA |
| Green Building Rough | 3/6/2024 | Approved | GABRIEL HERRERA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | GABRIEL HERRERA |
| Smoke Detectors | 3/6/2024 | Approved | GABRIEL HERRERA |
| Verify Sprinkler Sign Off | 3/6/2024 | Corrections Issued | GABRIEL HERRERA |
| BUILDING-Rough-Frame | 4/25/2024 | Approved | GABRIEL HERRERA |
| Final | 4/25/2024 | OK to Issue CofO | GABRIEL HERRERA |
| Green Building Final | 4/25/2024 | Approved | GABRIEL HERRERA |