10113 N DEMPSEY AVE 91343

Certificate Information: 10113 N DEMPSEY AVE 91343

Application / Permit
22010-20000-03740
Plan Check / Job No.
B22VN11527
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) detached garage to ADU with addition per ordinance LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 10/19/2022
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 HANS SANTIAGO
Corrections Issued 8/4/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/5/2022 HANS SANTIAGO
Plan Check Approved 10/18/2022 ANDREW SANTIAGO
Issued 10/19/2022 APPLICANT
CofO in Progress 3/9/2023 JAVIER RAMOS JR
CofO Issued 3/28/2023 MICHAEL SMITH
Permit Finaled 3/28/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/13/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 9/16/2022 KIRK LINKLATER
Construction near power lines Cleared 9/17/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/5/2022 COLIN LOREDO
Sewer availability Cleared 10/5/2022 COLIN LOREDO
Low Impact Development Cleared 10/17/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/17/2022 COLIN LOREDO
GPI Written Notices Cleared 10/18/2022 FARSHAD ALIMOHAMADI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/26/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/31/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 10/31/2022 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 11/3/2022 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 11/7/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/23/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 12/5/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 12/5/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/5/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/5/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 12/5/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/5/2022 Corrections Issued JAVIER RAMOS JR
Insulation 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/14/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 12/14/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/14/2022 Approved JAVIER RAMOS JR
Insulation 12/14/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 12/14/2022 Not Ready for Inspection JAVIER RAMOS JR
Shower Pan 12/14/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/20/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/20/2022 Approved JAVIER RAMOS JR
Insulation 12/20/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/20/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/20/2022 Approved JAVIER RAMOS JR
Sewer 1/23/2023 Approved JAVIER RAMOS JR
Underground Mechanical 1/23/2023 Approved JAVIER RAMOS JR
Service/Power Release 1/31/2023 Not Ready for Inspection JOHN COLEMAN
Final 2/14/2023 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/14/2023 Approved JAVIER RAMOS JR
Final 2/22/2023 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 3/9/2023 Approved JAVIER RAMOS JR