8614 N MASON AVE 91306
Certificate Information: 8614 N MASON AVE 91306
- Application / Permit
- 22010-20000-03734
- Plan Check / Job No.
- B22VN11492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Garage conversion with addition to ADU per WFPP, per ordinance “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2022 | MINA HABILI |
| Corrections Issued | 8/4/2022 | MINA HABILI |
| Applicant returned to address corrections | 11/15/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 11/17/2022 | KHUONG TRUONG |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | JEFFREY HARTLINE |
| No Progress | 4/11/2024 | SEAN WIRCH |
| CofO in Progress | 8/8/2024 | JEFFREY HARTLINE |
| Permit Finaled | 8/8/2024 | JOHN JANSON |
| CofO Issued | 8/8/2024 | JOHN JANSON |
| Permit Finaled | 8/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2023 | Partial Approval | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 1/26/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/30/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 1/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/14/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/14/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/19/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/24/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/24/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 8/7/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 9/8/2023 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Final | 9/14/2023 | Corrections Issued | JEFFREY HARTLINE |
| Service/Power Release | 9/14/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Gas Test | 10/3/2023 | Approved | JEFFREY HARTLINE |
| Grounding or Bonding | 10/3/2023 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 10/3/2023 | Partial Inspection | JEFFREY HARTLINE |
| Green Building Final | 10/13/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 10/13/2023 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 10/13/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 11/20/2023 | Approved | JEFFREY HARTLINE |
| Final | 11/20/2023 | Corrections Issued | JEFFREY HARTLINE |
| Smoke Detectors | 11/20/2023 | Approved | JEFFREY HARTLINE |
| Final | 12/1/2023 | OK to Issue CofO | JEFFREY HARTLINE |
| Special/Order Compliance | 4/11/2024 | Corrections Issued | JEFFREY HARTLINE |
| Special/Order Compliance | 7/22/2024 | Approved | JEFFREY HARTLINE |
| Final | 8/8/2024 | OK to Issue CofO | JEFFREY HARTLINE |