1667 N SARGENT CT 90026
Certificate Information: 1667 N SARGENT CT 90026
- Application / Permit
- 22010-20000-03723
- Plan Check / Job No.
- B22VN11462
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d) (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 10/6/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/25/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Applicant returned to address corrections | 7/11/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/10/2023 | NILOOFAR MEHRAIN |
| Issued | 10/6/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | JEANIE LAM |
| Permit | Cleared | 3/6/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/14/2023 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/1/2023 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 7/11/2023 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 7/11/2023 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 8/14/2023 | JEANIE LAM |
Contact Information
| Contractor | B C Design And Development Inc; Lic. No.: 1022562-B | PO BOX 1875 STUDIO CITY, CA 91604 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 10/20/2023 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/31/2024 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 2/15/2024 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 3/6/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/29/2024 | Approved | THOMAS LOGRASSO |
| Deputy Steel/Welding | 4/10/2024 | Conditional Approval | THOMAS LOGRASSO |
| Pre-Inspection | 10/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/25/2025 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/10/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 6/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/16/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/16/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/18/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/24/2025 | Approved | ALEX COLIN |
| Shower Pan | 7/30/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/1/2025 | Approved | ALEX COLIN |