17456 W HATTERAS ST 91316
Certificate Information: 17456 W HATTERAS ST 91316
- Application / Permit
- 22010-20000-03721
- Plan Check / Job No.
- B22VN11458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 27' 6" IRR.-SHAPED DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 8/1/2022 | APPLICANT |
| Corrections Issued | 8/16/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/30/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/6/2023 | MOHAMMAD ESMAILI |
| Issued | 1/6/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | JON MCHUGH |
| CofO in Progress | 5/14/2024 | JON MCHUGH |
| CofO in Progress | 9/27/2024 | MORRIS JACKSON |
| Permit Finaled | 11/14/2024 | JOHN JANSON |
| CofO Issued | 11/14/2024 | JOHN JANSON |
| Permit Finaled | 11/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/12/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 12/7/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/13/2022 | CARLOS AGUILERA |
| ZI | Cleared | 12/22/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/27/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/18/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 9/18/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 9/21/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/25/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 10/17/2023 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 10/19/2023 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 10/24/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 10/24/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 10/24/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 10/24/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 10/30/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 10/30/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JON MCHUGH |
| Final | 11/2/2023 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 11/2/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 11/2/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/2/2023 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | JON MCHUGH |
| Insulation | 11/6/2023 | Conditional Approval | JON MCHUGH |
| Drywall Nailing | 11/9/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/9/2023 | Approved | JON MCHUGH |
| Final | 12/18/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 12/18/2023 | Approved | JON MCHUGH |
| Green Building Final | 12/18/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 12/18/2023 | Approved | JON MCHUGH |
| Final | 3/27/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 3/27/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 3/27/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 4/18/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 4/18/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 4/18/2024 | Approved | JON MCHUGH |
| Service/Power Release | 4/18/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/9/2024 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 5/9/2024 | Approved | JON MCHUGH |
| Final | 5/14/2024 | Corrections Issued | JON MCHUGH |
| Final | 8/29/2024 | Corrections Issued | MORRIS JACKSON |
| Final | 9/27/2024 | OK to Issue CofO | MORRIS JACKSON |