16652 W MCCORMICK ST 91436

Certificate Information: 16652 W MCCORMICK ST 91436

Application / Permit
22010-20000-03720
Plan Check / Job No.
B22VN11445
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-0" x 14'-0" DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) . ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 8/2/2022 ALFRED RAMIREZ
Corrections Issued 8/2/2022 ALFRED RAMIREZ
Building Plans Picked Up 8/4/2022 APPLICANT
Plan Check Approved 8/10/2022 OMAR GARNICA
Issued 8/10/2022 APPLICANT
CofO in Progress 2/15/2023 VINCENT HANLEY
Permit Finaled 3/7/2023 JOHN JANSON
CofO Issued 3/7/2023 JOHN JANSON
Permit Finaled 3/7/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/5/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/5/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 8/5/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/5/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2022 Approved VINCENT HANLEY
PLUMBING-Rough 9/16/2022 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 9/23/2022 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval VINCENT HANLEY
Sewer 9/27/2022 Approved VINCENT HANLEY
Underground Mechanical 9/27/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/4/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/4/2022 Approved VINCENT HANLEY
Green Building Rough 10/4/2022 Approved VINCENT HANLEY
HVAC-Rough 10/4/2022 Approved VINCENT HANLEY
MERV13>=Rough 10/4/2022 Approved VINCENT HANLEY
PLUMBING-Rough 10/4/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/4/2022 Not Ready for Inspection VINCENT HANLEY
Insulation 10/12/2022 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 10/12/2022 Approved JESUS PINEDA
Shower Pan 10/12/2022 Approved JESUS PINEDA
Insulation 10/19/2022 Conditional Approval JESUS PINEDA
Underground Mechanical 10/19/2022 Approved JESUS PINEDA
Drywall Nailing 10/28/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/27/2023 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 1/27/2023 Approved DAVID SANDOVAL
Final 1/27/2023 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 1/27/2023 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 1/27/2023 Approved DAVID SANDOVAL
MERV13>=Final 1/27/2023 Approved DAVID SANDOVAL
PLUMBING-Final 1/27/2023 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Not Ready DAVID SANDOVAL
Service/Power Release 1/27/2023 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 1/27/2023 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 1/27/2023 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/14/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 2/14/2023 Approved VINCENT HANLEY
Final 2/14/2023 OK to Issue CofO VINCENT HANLEY
Green Building Final 2/14/2023 Approved VINCENT HANLEY
HVAC-Final 2/14/2023 Approved VINCENT HANLEY
PLUMBING-Final 2/14/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 2/14/2023 Approved VINCENT HANLEY