8045 N NORWICH AVE 91402

Certificate Information: 8045 N NORWICH AVE 91402

Application / Permit
22010-20000-03699
Plan Check / Job No.
B22VN11409
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 20'-10" X 24' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 5/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 RAPHAEL ROSAS
Corrections Issued 9/2/2022 RAPHAEL ROSAS
Quality Review Completed 9/8/2022 STEVEN KIM
Applicant returned to address corrections 7/5/2023 RAPHAEL ROSAS
Applicant returned to address corrections 8/4/2023 RAPHAEL ROSAS
Plan Check Approved 8/23/2023 RAPHAEL ROSAS
Issued 8/31/2023 APPLICANT
CofO in Progress 4/19/2024 KIRK SANDERS
Permit Finaled 5/2/2024 RUBEN SALAS
CofO Issued 5/2/2024 RUBEN SALAS
Permit Finaled 5/2/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/14/2022 COLIN LOREDO
Sewer availability Cleared 9/14/2022 COLIN LOREDO
Construction near power lines Cleared 7/25/2023 TINA MIRANDA
Low Impact Development Cleared 7/26/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 7/27/2023 COLIN LOREDO
Address approval Cleared 7/28/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer He,, Zizhao; Lic. No.: NA6930       ,
Engineer He,, Zizhao; Lic. No.: S6930 20182 MCKINLEY LN      HUNTINGTON BEACH, CA 92646

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 9/18/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 9/21/2023 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 9/22/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/17/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/17/2023 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 10/17/2023 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 10/17/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/6/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/6/2023 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 11/6/2023 Conditional Approval MISAEL ESPARZA
Wood Frame 11/13/2023 Approved GREGG CUMMINGS
Insulation 11/28/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/28/2023 Approved DAVID ANDERSON
Drywall Nailing 12/8/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 12/8/2023 Approved CHRISTOPHER ROJAS
Underground Mechanical 1/31/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/2/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 2/2/2024 Approved CHRISTOPHER ROJAS
Final 4/1/2024 Corrections Issued DAVID MATSON
Green Building Final 4/1/2024 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved DAVID MATSON
Service/Power Release 4/1/2024 Not Ready for Inspection DAVID MATSON
Smoke Detectors 4/1/2024 Approved DAVID MATSON
Final 4/18/2024 OK to Issue CofO KIRK SANDERS
Service/Power Release 4/18/2024 Approved KIRK SANDERS