829 1/2 E 81ST ST 90001

Certificate Information: 829 1/2 E 81ST ST 90001

Application / Permit
22010-20000-03689
Plan Check / Job No.
B22VN11397
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/15/2022
Issuing Office
Current Status
CofO Issued on 5/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 DANIEL YIP
Corrections Issued 8/1/2022 DANIEL YIP
Applicant returned to address corrections 8/29/2022 DANIEL YIP
Applicant returned to address corrections 8/31/2022 DANIEL YIP
Plan Check Approved 11/9/2022 DANIEL YIP
Issued 11/15/2022 APPLICANT
CofO in Progress 5/12/2023 MICHAEL LEWIS
Permit Finaled 5/19/2023 DEROLD HAUFF
CofO Issued 5/19/2023 DEROLD HAUFF
Permit Finaled 5/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/11/2022 JEANIE LAM
Sewer availability Cleared 8/11/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/12/2022 JEANIE LAM
Construction within easement Cleared 10/24/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/30/2022 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 12/23/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 1/20/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Not Ready LILIANA PORTILLO
Sewer 1/20/2023 Approved LILIANA PORTILLO
Underground Mechanical 1/20/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 2/21/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 2/21/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/21/2023 Corrections Issued LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 2/24/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 3/3/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/3/2023 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 3/3/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Approved LILIANA PORTILLO
Insulation 3/8/2023 Approved LILIANA PORTILLO
Drywall Nailing 3/17/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/17/2023 Approved LILIANA PORTILLO
Underground Mechanical 3/30/2023 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 4/17/2023 Approved LILIANA PORTILLO
Final 4/17/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 4/17/2023 Approved LILIANA PORTILLO
Final 5/5/2023 Conditional Approval MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved MICHAEL LEWIS
Final 5/12/2023 OK to Issue CofO MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Approved MICHAEL LEWIS