6830 N LUBAO AVE 91306
Certificate Information: 6830 N LUBAO AVE 91306
- Application / Permit
- 22010-20000-03681
- Plan Check / Job No.
- B22VN11351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 7/21/2023
- Issuing Office
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/5/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/12/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/6/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/16/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 2/17/2023 | MICHAEL LOPEZ |
| No Progress | 2/22/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 3/30/2023 | MICHAEL LOPEZ |
| Issued | 7/21/2023 | APPLICANT |
| CofO in Progress | 1/30/2025 | ALEXANDER HANDY |
| CofO in Progress | 2/14/2025 | HENRY KIM |
| Permit Finaled | 5/8/2025 | JOHN JANSON |
| CofO Issued | 5/8/2025 | JOHN JANSON |
| Permit Finaled | 5/8/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | CARLOS AGUILERA |
| Permit | Cleared | 8/11/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/11/2022 | CARLOS AGUILERA |
| ZI | Cleared | 8/24/2022 | ASHLEY RODARTE |
| Hydrant and Access approval | Cleared | 9/25/2022 | RUEL COLE |
| Low Impact Development | Cleared | 10/4/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/7/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lota,, Dante S; Lic. No.: S2314 | 19325 TRENTHAM AVE CERRITOS, CA 90701 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2023 | Partial Inspection | HORACE FULTZ |
| PLUMBING-Rough | 11/15/2023 | No Access for Inspection | ALEXANDER HANDY |
| Green Building Rough | 11/17/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 11/27/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/1/2023 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/13/2023 | Approved | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 1/26/2024 | Conditional Approval | ALEXANDER HANDY |
| Wood Frame | 2/27/2024 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 3/26/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Wood Frame | 4/2/2024 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 6/10/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 6/10/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/1/2024 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 7/1/2024 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 7/1/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/10/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/10/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/30/2024 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 8/19/2024 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/29/2024 | Corrections Issued | SCOTT SOBEL |
| Drywall Nailing | 8/29/2024 | Approved | SCOTT SOBEL |
| Sewer | 10/22/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 10/28/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 11/8/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/14/2025 | Corrections Issued | ALEXANDER HANDY |
| Final | 1/14/2025 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Final | 1/14/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Final | 1/14/2025 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/29/2025 | Approved | ALEXANDER HANDY |
| Final | 1/29/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 1/29/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 1/29/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 1/29/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/29/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/29/2025 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 1/29/2025 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 2/18/2025 | Corrections Issued | ALEXANDER HANDY |
| Deputy Wood Construction | 2/19/2025 | Conditional Approval | ALEXANDER HANDY |