225 1/2-227 1/2 E 85TH ST 90003

Certificate Information: 225 1/2-227 1/2 E 85TH ST 90003

Application / Permit
22010-20000-03666
Plan Check / Job No.
B22VN11331
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan TWO (2) NEW DETACHED ACCESSORY DWELLING UNITS 30'-4" x 32'-0"
Permit Issued
Issued on 2/22/2023
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 CRYSTEL MAALOUF
Corrections Issued 8/31/2022 CRYSTEL MAALOUF
Quality Review Completed 8/31/2022 GARO TELMI
Applicant returned to address corrections 9/19/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 1/12/2023 CRYSTEL MAALOUF
Plan Check Approved 1/31/2023 CRYSTEL MAALOUF
Issued 2/22/2023 APPLICANT
CofO in Progress 7/3/2024 MICHAEL LEWIS
Permit Finaled 7/9/2024 DEROLD HAUFF
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 9/20/2022 AMAAN MALIK
Sewer availability Cleared 9/20/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/23/2022 AMAAN MALIK
Low Impact Development Cleared 12/29/2022 LONDY ALVARADO

Contact Information

Architect Carrillo,, Jessie; Lic. No.: C32448 13006 PHILADELPHIA ST #506      WHITTIER, CA 90601
Contractor Oscar'S Handyman Service; Lic. No.: 1014696-B       ,
Engineer Contreras,, Humberto; Lic. No.: C83240 10614 PARISE DR      WHITTIER, CA 90604

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/8/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 3/8/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/20/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 4/20/2023 Approved LILIANA PORTILLO
Deputy Wood Construction 4/27/2023 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 4/28/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Conditional Approval MICHAEL LEWIS
HVAC-Rough 4/28/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/12/2023 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 5/12/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/17/2023 Approved MICHAEL LEWIS
Green Building Rough 5/17/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/17/2023 Approved MICHAEL LEWIS
Insulation 5/22/2023 Approved MICHAEL LEWIS
Drywall Nailing 5/26/2023 Approved MICHAEL LEWIS
Sewer 6/7/2023 Approved STUART CHAPMAN
Underground Mechanical 6/7/2023 Partial Inspection STUART CHAPMAN
ELECTRICAL-Final 11/20/2023 Corrections Issued MICHAEL LEWIS
Gas Test 11/20/2023 Approved MICHAEL LEWIS
Pre-Inspection 11/30/2023 Approved MICHAEL LEWIS
Final 3/7/2024 Corrections Issued MICHAEL LEWIS
Gas Test 3/7/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 3/7/2024 Approved MICHAEL LEWIS
Smoke Detectors 3/7/2024 Approved MICHAEL LEWIS
Final 4/5/2024 No Access for Inspection MICHAEL LEWIS
Final 4/10/2024 Partial Inspection MICHAEL LEWIS
Special/Order Compliance 5/1/2024 Corrections Issued DAVID FEILER
Final 5/20/2024 OK to Issue CofO MICHAEL LEWIS
Special/Order Compliance 6/26/2024 Corrections Issued MICHAEL LEWIS