11944 W MIRANDA ST 91607

Certificate Information: 11944 W MIRANDA ST 91607

Application / Permit
22010-20000-03664
Plan Check / Job No.
B22VN11316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 25'-2"X42' ONE STORY ACCESSORY DWELLING UNIT WITH ONE OPEN PARKING PROVIDED [PER LAMC 12.22A33(C) AND (D)] .
Permit Issued
Issued on 2/17/2023
Issuing Office
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 DAWN MC NULTY
Corrections Issued 8/24/2022 DAWN MC NULTY
Quality Review Completed 8/30/2022 STEVEN KIM
Building Plans Picked Up 8/31/2022 APPLICANT
Applicant returned to address corrections 11/21/2022 DAWN MC NULTY
Applicant returned to address corrections 2/10/2023 DAWN MC NULTY
Plan Check Approved 2/15/2023 DAWN MC NULTY
Issued 2/17/2023 APPLICANT
CofO in Progress 2/3/2025 JENNIFER RABUCHIN
No Progress 4/24/2025 RAUL OLAGI
CofO in Progress 4/24/2025 RAUL OLAGI
CofO in Progress 6/24/2025 JENNIFER RABUCHIN
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/27/2022 DAGOVERTO GUERRERO
Permit Cleared 10/28/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/31/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 11/9/2022 CHRIS VONG
Hydrant and Access approval Cleared 11/13/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 11/16/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/16/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/13/2023 RIDWAN HARDY
Construction within easement Cleared 1/24/2023 RIDWAN HARDY

Contact Information

Contractor Trig Builders Inc; Lic. No.: 1030887-B 6442 COLDWATER CANYON AVE 111      NORTH HOLLYWOOD, CA 91606
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/27/2023 Corrections Issued JOHN HAYES
Underground Mechanical 5/5/2023 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/28/2023 Approved JOHN HAYES
Special/Order Compliance 7/7/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 8/11/2023 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 8/11/2023 Corrections Issued DAVID MATSON
Green Building Rough 8/11/2023 Not Ready for Inspection DAVID MATSON
MERV13>=Rough 8/11/2023 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 8/11/2023 Corrections Issued DAVID MATSON
Verify Sprinkler Sign Off 8/11/2023 Conditional Approval DAVID MATSON
HVAC-Rough 8/14/2023 Approved DAVID MATSON
PLUMBING-Rough 8/14/2023 Approved DAVID MATSON
Rough-Elec/Plmb/HVAC 8/14/2023 Approved DAVID MATSON
Wood Frame 8/14/2023 Approved DAVID MATSON
Insulation 8/22/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/22/2023 Partial Approval JENNIFER RABUCHIN
Shower Pan 8/22/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 8/24/2023 Approved JENNIFER RABUCHIN
Green Building Rough 8/24/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/24/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/28/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/28/2023 Corrections Issued JENNIFER RABUCHIN
Final 9/28/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/28/2023 Approved JENNIFER RABUCHIN
Green Building Final 9/28/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 9/28/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 9/28/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 9/28/2023 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 9/28/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/28/2023 Approved JENNIFER RABUCHIN
Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/12/2023 Approved JENNIFER RABUCHIN
Service/Power Release 10/12/2023 Not Required JENNIFER RABUCHIN
ELECTRICAL-Final 12/8/2023 Approved JENNIFER RABUCHIN
Final 12/8/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/8/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/8/2023 Approved JENNIFER RABUCHIN
Final 2/3/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 2/3/2025 Corrections Issued JENNIFER RABUCHIN
Final 4/24/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 4/24/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/24/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 6/24/2025 Approved JENNIFER RABUCHIN