515 W 57TH ST 90037
Certificate Information: 515 W 57TH ST 90037
- Application / Permit
- 22010-20000-03658
- Plan Check / Job No.
- B22VN11311
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'-6" x 45' TWO-STORY DET. ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33 (c)-(d)) W/ ATT. 3-CAR GARAGE
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/17/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Plan Check Approved | 1/24/2023 | SEAN SHAHMIRI |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 4/10/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/10/2024 | DEROLD HAUFF |
| CofO Issued | 4/10/2024 | DEROLD HAUFF |
| Permit Finaled | 4/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | CINDY QI |
| Sewer availability | Cleared | 8/22/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 10/22/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 11/14/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | CINDY QI |
| Construction near power lines | Cleared | 1/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/16/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/20/2023 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 3/22/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/22/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 4/13/2023 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/2/2023 | Partial Inspection | STUART CHAPMAN |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 6/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 6/2/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 6/6/2023 | Conditional Approval | SABAS ALONSO |
| HVAC-Rough | 6/6/2023 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 6/6/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/12/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 6/12/2023 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/12/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/20/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 6/20/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 6/27/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/27/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/27/2023 | Approved | SABAS ALONSO |
| Shower Pan | 6/27/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/7/2023 | Corrections Issued | ANTHONY EGSON |
| MERV13>=Rough | 7/7/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 7/7/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/12/2023 | Conditional Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/12/2023 | Approved | SABAS ALONSO |
| Insulation | 7/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/27/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 7/27/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 8/7/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/7/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/15/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/15/2023 | Partial Approval | CRAIG DAVIS |
| Sewer | 11/15/2023 | Approved | CRAIG DAVIS |
| Underground Mechanical | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/11/2023 | No Access for Inspection | CRAIG DAVIS |
| Service/Power Release | 12/11/2023 | No Access for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/25/2024 | Partial Approval | RONNIE MINDANAO |
| Final | 1/25/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 1/25/2024 | Approved | RONNIE MINDANAO |
| MERV13>=Final | 1/25/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| MERV13>=Rough | 1/25/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 1/25/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 1/25/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| Final | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| MERV13>=Final | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| MERV13>=Rough | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 2/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/7/2024 | Approved | RONNIE MINDANAO |
| Final | 2/7/2024 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 2/7/2024 | Approved | RONNIE MINDANAO |
| MERV13>=Final | 2/7/2024 | Approved | RONNIE MINDANAO |
| MERV13>=Rough | 2/7/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 2/7/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 2/7/2024 | Approved | RONNIE MINDANAO |
| Final | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/26/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Approved | RONNIE MINDANAO |
| Service/Power Release | 2/26/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 3/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 3/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 4/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/9/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/9/2024 | Approved | ALEJANDRO DE ARTOLA |