515 W 57TH ST 90037

Certificate Information: 515 W 57TH ST 90037

Application / Permit
22010-20000-03658
Plan Check / Job No.
B22VN11311
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-6" x 45' TWO-STORY DET. ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33 (c)-(d)) W/ ATT. 3-CAR GARAGE
Permit Issued
Issued on 1/24/2023
Issuing Office
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 SEAN SHAHMIRI
Corrections Issued 8/17/2022 SEAN SHAHMIRI
Quality Review Completed 8/24/2022 OMID HEDAYAT
Building Plans Picked Up 8/25/2022 APPLICANT
Plan Check Approved 1/24/2023 SEAN SHAHMIRI
Issued 1/24/2023 APPLICANT
CofO in Progress 4/10/2024 ALEJANDRO DE ARTOLA
Permit Finaled 4/10/2024 DEROLD HAUFF
CofO Issued 4/10/2024 DEROLD HAUFF
Permit Finaled 4/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/22/2022 CINDY QI
Sewer availability Cleared 8/22/2022 CINDY QI
Hydrant and Access approval Cleared 10/22/2022 GILBERT URREA
Low Impact Development Cleared 11/14/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/14/2022 CINDY QI
Construction near power lines Cleared 1/18/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/16/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 3/20/2023 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/22/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 3/22/2023 Approved SABAS ALONSO
Green Building Rough 4/13/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 6/2/2023 Partial Inspection STUART CHAPMAN
Green Building Rough 6/2/2023 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 6/2/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 6/2/2023 Not Ready for Inspection STUART CHAPMAN
Wood Frame 6/2/2023 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 6/6/2023 Conditional Approval SABAS ALONSO
HVAC-Rough 6/6/2023 Corrections Issued SCOTT FINNILA
Wood Frame 6/6/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 6/12/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval STUART CHAPMAN
HVAC-Rough 6/12/2023 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 6/12/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 6/20/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/20/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 6/27/2023 Approved SABAS ALONSO
HVAC-Rough 6/27/2023 Approved SABAS ALONSO
PLUMBING-Rough 6/27/2023 Approved SABAS ALONSO
Shower Pan 6/27/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 7/7/2023 Corrections Issued ANTHONY EGSON
MERV13>=Rough 7/7/2023 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 7/7/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 7/12/2023 Conditional Approval SABAS ALONSO
Verify Sprinkler Sign Off 7/12/2023 Approved SABAS ALONSO
Insulation 7/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 7/27/2023 Approved BRENDAN MORELLI
Shower Pan 7/27/2023 Approved BRENDAN MORELLI
Drywall Nailing 8/7/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 8/7/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 8/15/2023 Approved SABAS ALONSO
PLUMBING-Rough 11/15/2023 Partial Approval CRAIG DAVIS
Sewer 11/15/2023 Approved CRAIG DAVIS
Underground Mechanical 11/15/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/11/2023 No Access for Inspection CRAIG DAVIS
Service/Power Release 12/11/2023 No Access for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Not Ready CRAIG DAVIS
BUILDING-Rough-Frame 1/25/2024 Partial Approval RONNIE MINDANAO
Final 1/25/2024 Corrections Issued RONNIE MINDANAO
Green Building Final 1/25/2024 Approved RONNIE MINDANAO
MERV13>=Final 1/25/2024 Not Ready for Inspection RONNIE MINDANAO
MERV13>=Rough 1/25/2024 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 1/25/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 1/25/2024 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 2/1/2024 No Access for Inspection RONNIE MINDANAO
Final 2/1/2024 No Access for Inspection RONNIE MINDANAO
MERV13>=Final 2/1/2024 No Access for Inspection RONNIE MINDANAO
MERV13>=Rough 2/1/2024 No Access for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 2/1/2024 No Access for Inspection RONNIE MINDANAO
Smoke Detectors 2/1/2024 No Access for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 2/7/2024 Approved RONNIE MINDANAO
Final 2/7/2024 Corrections Issued RONNIE MINDANAO
Gas Test 2/7/2024 Approved RONNIE MINDANAO
MERV13>=Final 2/7/2024 Approved RONNIE MINDANAO
MERV13>=Rough 2/7/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 2/7/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 2/7/2024 Approved RONNIE MINDANAO
Final 2/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/21/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 2/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/26/2024 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved RONNIE MINDANAO
Service/Power Release 2/26/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Final 3/29/2024 Not Ready for Inspection SABAS ALONSO
Final 3/29/2024 Not Ready for Inspection SABAS ALONSO
Service/Power Release 3/29/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 4/9/2024 Approved ALEJANDRO DE ARTOLA
Final 4/9/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 4/9/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/9/2024 Approved ALEJANDRO DE ARTOLA