7043 N YOLANDA AVE 91335
Certificate Information: 7043 N YOLANDA AVE 91335
- Application / Permit
- 22010-20000-03656
- Plan Check / Job No.
- B22VN11295
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW DETACHED ACCESSORY LIVING QUARTERS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/23/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Plan Check Approved | 12/29/2022 | SELLA BENYAMIN |
| Issued | 12/29/2022 | APPLICANT |
| CofO in Progress | 7/23/2024 | JEFFREY BULL |
| Permit Finaled | 4/7/2025 | JOHN JANSON |
| CofO Issued | 4/7/2025 | JOHN JANSON |
| Permit Finaled | 4/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/13/2022 | COLIN LOREDO |
| ZA Case | Cleared | 12/13/2022 | STEVEN WECHSLER |
| ZI | Cleared | 12/13/2022 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 12/22/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/22/2022 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rubio,, Ramon; Lic. No.: S6480 | 5842 WARWICK CIRCLE LA PALMA, CA 90623 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2023 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Partial Approval | JEFFREY BULL |
| Deputy Wood Construction | 8/9/2023 | Conditional Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Not Ready for Inspection | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/23/2023 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Approved | HENRY KIM |
| Green Building Rough | 10/23/2023 | Approved | HENRY KIM |
| HVAC-Rough | 10/23/2023 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 10/23/2023 | Approved | HENRY KIM |
| PLUMBING-Rough | 10/23/2023 | Approved | HENRY KIM |
| Underground Mechanical | 10/23/2023 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 10/23/2023 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/30/2023 | Approved | JEFFREY BULL |
| Insulation | 10/30/2023 | Approved | JEFFREY BULL |
| Sewer | 10/30/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 11/27/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 11/27/2023 | Approved | JEFFREY BULL |
| Final | 7/9/2024 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 7/9/2024 | Approved | JEFFREY BULL |
| Green Building Final | 7/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 7/9/2024 | Not Required | JEFFREY BULL |
| Smoke Detectors | 7/9/2024 | Approved | JEFFREY BULL |
| Final | 7/23/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 7/23/2024 | Approved | JEFFREY BULL |