11142 W KLING ST 91602
Certificate Information: 11142 W KLING ST 91602
- Application / Permit
- 22010-20000-03632
- Plan Check / Job No.
- B22VN11265
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 Story Single Family Dwelling WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | CARLOS MONTES |
| Corrections Issued | 8/19/2022 | CARLOS MONTES |
| Quality Review Completed | 8/23/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/29/2022 | CARLOS MONTES |
| Plan Check Approved | 12/23/2022 | CARLOS MONTES |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 1/27/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 1/29/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 2/18/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
| CofO Issued | 3/13/2025 | RUBEN SALAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 9/12/2022 | MATTHEW CRAIG |
| Sewer availability | Cleared | 9/12/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 12/8/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/13/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/16/2023 | Approved | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/17/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Steel/Welding | 3/9/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 5/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/20/2023 | Partial Approval | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 6/30/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 6/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 7/5/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/5/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 7/5/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/5/2023 | Approved | JACK KARGODORIAN |
| Insulation | 8/4/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 8/8/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/15/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/24/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/13/2023 | Approved | JUAN VALENZUELA |
| Sewer | 3/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 5/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 5/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 5/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/7/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/7/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/7/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/7/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 11/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 11/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/27/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 1/27/2025 | Approved | CHRISTOPHER ROJAS |