10936 1/2 N BURNET AVE 91345
Certificate Information: 10936 1/2 N BURNET AVE 91345
- Application / Permit
- 22010-20000-03625
- Plan Check / Job No.
- B22VN11258
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan New detached 2-story Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D throughout.
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/1/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 8/8/2022 | CHARLES CHANG |
| Plan Check Approved | 11/7/2022 | FARSHAD ALIMOHAMADI |
| Issued | 11/15/2022 | APPLICANT |
| CofO in Progress | 10/5/2023 | JENNIFER RABUCHIN |
| No Progress | 12/13/2023 | ROBERT GOLD |
| CofO in Progress | 12/13/2023 | ROBERT GOLD |
| CofO in Progress | 12/14/2023 | ROBERT GOLD |
| No Progress | 12/14/2023 | ROBERT GOLD |
| CofO in Progress | 12/14/2023 | ROBERT GOLD |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 9/22/2022 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 9/27/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/19/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: NA43590 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 11/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 12/14/2022 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/9/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 1/9/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2023 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 1/9/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 1/9/2023 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/9/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/11/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/11/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/23/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 1/23/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 1/25/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/25/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/30/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/30/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 3/29/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 4/4/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/10/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/10/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/10/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 7/25/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | DAVID MATSON |
| Final | 8/11/2023 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 8/11/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 8/15/2023 | Approved | MATTHEW NELSON |
| Final | 8/15/2023 | Partial Inspection | MATTHEW NELSON |
| Final | 9/7/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 9/7/2023 | Not Required | JENNIFER RABUCHIN |