2019 1/2 S HARCOURT AVE 90016

Certificate Information: 2019 1/2 S HARCOURT AVE 90016

Application / Permit
22010-20000-03606
Plan Check / Job No.
B22VN11245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 30' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ATTACHED TO EXISTING DETACHED GARAGE
Permit Issued
Issued on 8/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 SELLA BENYAMIN
Corrections Issued 8/22/2022 SELLA BENYAMIN
Quality Review Completed 8/24/2022 STEVEN KIM
Building Plans Picked Up 8/25/2022 APPLICANT
Plan Check Approved 10/28/2022 SELLA BENYAMIN
Issued 8/17/2023 APPLICANT
CofO in Progress 5/6/2025 WILLIAM SIERRA
No Progress 5/15/2025 DEROLD HAUFF
CofO in Progress 5/15/2025 DEROLD HAUFF
Permit Finaled 6/11/2025 DEROLD HAUFF
CofO Issued 6/11/2025 DEROLD HAUFF
Permit Finaled 6/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/24/2022 CELINA MORENO
Sewer availability Cleared 8/24/2022 CELINA MORENO
Low Impact Development Cleared 9/14/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 9/15/2022 CELINA MORENO

Contact Information

Contractor Golden Construction Group Llc; Lic. No.: 1078364-B 6920 CHIMINEAS AVENUE      RESEDA, CA 91335
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/24/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/31/2023 Corrections Issued CALEB MEISTER
Sewer 8/31/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 9/6/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 10/21/2024 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Rough 10/21/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Approved JUSTIN HAWLEY
HVAC-Rough 10/21/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 10/21/2024 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 10/22/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 10/22/2024 Approved JUSTIN HAWLEY
HVAC-Rough 10/22/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 10/22/2024 Approved JUSTIN HAWLEY
Insulation 10/25/2024 Conditional Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 10/25/2024 Partial Approval NICHOLAS LOPEZ
Drywall Nailing 11/13/2024 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 11/13/2024 Approved JOHN QUINTANILLA
Shower Pan 11/13/2024 Approved JOHN QUINTANILLA
Sewer 12/6/2024 Approved JUSTIN HAWLEY
Underground Mechanical 12/6/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 1/27/2025 Approved JUSTIN HAWLEY
Final 1/27/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 1/27/2025 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 1/27/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 1/27/2025 Approved JUSTIN HAWLEY
Final 5/5/2025 OK to Issue CofO WILLIAM SIERRA
Green Building Final 5/5/2025 Approved WILLIAM SIERRA
Service/Power Release 5/5/2025 Approved WILLIAM SIERRA