2019 1/2 S HARCOURT AVE 90016
Certificate Information: 2019 1/2 S HARCOURT AVE 90016
- Application / Permit
- 22010-20000-03606
- Plan Check / Job No.
- B22VN11245
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 30' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ATTACHED TO EXISTING DETACHED GARAGE
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/24/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Plan Check Approved | 10/28/2022 | SELLA BENYAMIN |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 5/6/2025 | WILLIAM SIERRA |
| No Progress | 5/15/2025 | DEROLD HAUFF |
| CofO in Progress | 5/15/2025 | DEROLD HAUFF |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
| CofO Issued | 6/11/2025 | DEROLD HAUFF |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | CELINA MORENO |
| Sewer availability | Cleared | 8/24/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 9/14/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/15/2022 | CELINA MORENO |
Contact Information
| Contractor | Golden Construction Group Llc; Lic. No.: 1078364-B | 6920 CHIMINEAS AVENUE RESEDA, CA 91335 |
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/24/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/31/2023 | Corrections Issued | CALEB MEISTER |
| Sewer | 8/31/2023 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 9/6/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/21/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 10/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 10/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/22/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/22/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 10/22/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 10/22/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 10/25/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/25/2024 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 11/13/2024 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/13/2024 | Approved | JOHN QUINTANILLA |
| Shower Pan | 11/13/2024 | Approved | JOHN QUINTANILLA |
| Sewer | 12/6/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 12/6/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/27/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 1/27/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 1/27/2025 | Approved | JUSTIN HAWLEY |
| Final | 5/5/2025 | OK to Issue CofO | WILLIAM SIERRA |
| Green Building Final | 5/5/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 5/5/2025 | Approved | WILLIAM SIERRA |