16219 W COMMUNITY CT 91343
Certificate Information: 16219 W COMMUNITY CT 91343
- Application / Permit
- 22010-20000-03599
- Plan Check / Job No.
- B22VN11224
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD AND ATTACHED 2 CAR GARAGE and TRELLIS per SB9 Two-Unit Development Ca Govt Code 65852.21 ; fire sprinkler nfpa-13r
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Valley
- Current Status
- Issued on 9/15/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 8/18/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Plan Check Approved | 9/11/2023 | MOHAMMAD ESMAILI |
| Issued | 9/15/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 10/14/2022 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 10/17/2022 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 2/16/2023 | COLIN LOREDO |
| Construction within easement | Cleared | 3/9/2023 | TORI CHEN |
| Private sewage disp. approval | Cleared | 8/7/2023 | MICHAEL TEMPLE |
| Senate Bill 9 | Cleared | 8/23/2023 | RYAN LY |
| Construction near power lines | Cleared | 8/25/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 9/11/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/8/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/8/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 2/6/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Not Ready for Inspection | RAUL OLAGI |
| Deputy Wood Construction | 3/29/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 6/11/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/13/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 6/13/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 6/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 6/13/2024 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/14/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/14/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 6/14/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/14/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/18/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 6/18/2024 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 6/18/2024 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/24/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/24/2024 | Partial Approval | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 6/24/2024 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/27/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/27/2024 | Partial Approval | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 6/27/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Insulation | 7/3/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Insulation | 7/8/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 7/17/2024 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 7/22/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 9/9/2024 | Approved | RAUL OLAGI |
| Shower Pan | 9/9/2024 | Approved | RAUL OLAGI |
| Pre-Inspection | 5/12/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 6/10/2025 | Corrections Issued | MICHAEL CORTEZ |
| Underground Mechanical | 6/10/2025 | Partial Inspection | MICHAEL CORTEZ |
| Sewer | 8/19/2025 | Approved | GAREN HAYRAPETYAN |