13058 W PINNEY ST 91331

Certificate Information: 13058 W PINNEY ST 91331

Application / Permit
22010-20000-03596
Plan Check / Job No.
B22VN11223
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 16'-11" X 65'-5" 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED PATIO COVERS AND PARKING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT SEE COMMENTS
Permit Issued
Issued on 3/14/2025
Issuing Office
Current Status
CofO in Progress on 5/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/8/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/9/2022 OMID HEDAYAT
Building Plans Picked Up 8/12/2022 APPLICANT
Applicant returned to address corrections 4/27/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/10/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/30/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/3/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/12/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/27/2025 SEWADA ZADOORAN MILAGARDI
Issued 3/14/2025 APPLICANT
CofO in Progress 5/5/2026 MICHEL ABAJAN

Permit Application Clearance Information

Sewer availability Cleared 8/22/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/24/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 8/24/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/25/2022 DAGOVERTO GUERRERO
Clean Up Green Up Cleared 8/30/2022 CLAUDE GOODING
Miscellaneous Cleared 8/30/2022 CLAUDE GOODING
Hydrant and Access approval Cleared 9/28/2022 GILBERT URREA
Permit Cleared 9/28/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 9/28/2022 ADALBERTO VERA
Address approval Cleared 1/15/2025 RYAN CASTRO
Address approval Cleared 1/15/2025 RYAN CASTRO

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Advanced Construction; Lic. No.: 801955-B 4606 WILLIS AVE #307      SHERMAN OAKS, CA 91403
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2025 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 3/18/2025 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 3/18/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 3/18/2025 Partial Approval MICHEL ABAJAN
Sewer 3/18/2025 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 3/19/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 4/14/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/14/2025 Approved MICHEL ABAJAN
METHANE-Barrier 4/14/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 4/14/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 5/14/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval MICHEL ABAJAN
HVAC-Rough 5/28/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 5/28/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/2/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/2/2025 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 6/2/2025 Approved JENNIFER RABUCHIN
Insulation 6/23/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/23/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 7/3/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 7/3/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 9/2/2025 Partial Inspection MICHEL ABAJAN
Underground Mechanical 9/2/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 10/29/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/29/2025 Approved MICHEL ABAJAN
HVAC-Final 10/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/3/2025 Approved MICHEL ABAJAN
Final 12/3/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 12/3/2025 Approved MICHEL ABAJAN
HVAC-Final 12/3/2025 Approved MICHEL ABAJAN
METHANE-Final 12/3/2025 Approved MICHEL ABAJAN
METHANE-Rough 12/3/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/3/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 12/3/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 12/3/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/3/2025 Approved MICHEL ABAJAN
Final 4/28/2026 Corrections Issued JOSE AVILA
Final 5/4/2026 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/4/2026 Approved MICHEL ABAJAN