634 S ORANGE DR 90036

Certificate Information: 634 S ORANGE DR 90036

Application / Permit
22010-20000-03576
Plan Check / Job No.
B22VN11184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 198 SF PORTION OF (E) DETACHED GARAGE. CONVERT 17' X 14'-7" REMAINING PORTION OF DETACHED GARAGE AND ADD 17' X 27'-5" FOR NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/14/2023
Issuing Office
Current Status
CofO Issued on 4/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 RAPHAEL ROSAS
Corrections Issued 8/8/2022 RAPHAEL ROSAS
Quality Review Completed 8/10/2022 STEVEN KIM
Building Plans Picked Up 8/16/2022 APPLICANT
Applicant returned to address corrections 12/21/2022 RAPHAEL ROSAS
Applicant returned to address corrections 1/3/2023 RAPHAEL ROSAS
Applicant returned to address corrections 1/6/2023 RAPHAEL ROSAS
Applicant returned to address corrections 1/24/2023 RAPHAEL ROSAS
Plan Check Approved 2/3/2023 RAPHAEL ROSAS
Issued 3/14/2023 APPLICANT
CofO in Progress 4/11/2025 RONNIE MINDANAO
Permit Finaled 4/20/2025 DEROLD HAUFF
Permit Finaled 4/20/2025 DEROLD HAUFF
CofO Issued 4/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/13/2022 CINDY QI
Sewer availability Cleared 9/14/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/19/2022 CINDY QI
Low Impact Development Cleared 12/6/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/20/2022 CINDY QI
Construction near power lines Cleared 1/3/2023 WALTER RAMIREZ

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/31/2023 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 8/31/2023 Approved ROY SPAULDING
Footing/Foundation/Slab 8/31/2023 Approved ROY SPAULDING
METHANE-Barrier 8/31/2023 Approved ROY SPAULDING
METHANE-Subgrade 8/31/2023 Approved ROY SPAULDING
Underground Mechanical 8/31/2023 Approved ROY SPAULDING
METHANE-Rough 9/6/2023 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/12/2023 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 4/3/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 4/3/2024 Partial Inspection CRAIG DAVIS
ELECTRICAL-Rough 5/3/2024 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval JOSEPH MCGARRY
HVAC-Rough 5/3/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/3/2024 Approved JOSEPH MCGARRY
Underground Mechanical 5/3/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/8/2024 Approved RONNIE MINDANAO
Green Building Rough 5/8/2024 Approved RONNIE MINDANAO
Underground Mechanical 5/10/2024 Partial Approval JOSEPH MCGARRY
Insulation 6/7/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/7/2024 Partial Approval RICHARD DOCKUS
Drywall Nailing 6/14/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/14/2024 Partial Approval RICHARD DOCKUS
Shower Pan 6/14/2024 Approved RICHARD DOCKUS
Verify Rec and Parks Fee Memo 11/18/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 1/21/2025 Not Ready for Inspection RONNIE MINDANAO
Gas Test 1/21/2025 Approved RONNIE MINDANAO
HVAC-Final 1/21/2025 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Final 1/21/2025 Approved RONNIE MINDANAO
ELECTRICAL-Final 1/23/2025 Not Ready for Inspection RONNIE MINDANAO
HVAC-Final 1/23/2025 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 1/24/2025 Approved RONNIE MINDANAO
HVAC-Final 1/24/2025 Approved RONNIE MINDANAO
Final 1/28/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 1/28/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved RONNIE MINDANAO
Service/Power Release 1/28/2025 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 1/28/2025 Approved RONNIE MINDANAO
Final 1/31/2025 Corrections Issued RONNIE MINDANAO
Service/Power Release 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
Final 4/7/2025 Corrections Issued RONNIE MINDANAO
Final 4/10/2025 OK to Issue CofO RONNIE MINDANAO
Service/Power Release 4/10/2025 Approved RONNIE MINDANAO