14519 W SAN JOSE ST 91345

Certificate Information: 14519 W SAN JOSE ST 91345

Application / Permit
22010-20000-03535
Plan Check / Job No.
B22VN11049
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO-STORY 22'-6" X 27'-6"ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/11/2023
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/11/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/19/2022 OMID HEDAYAT
Building Plans Picked Up 8/25/2022 APPLICANT
Applicant returned to address corrections 12/22/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/11/2023 SEWADA ZADOORAN MILAGARDI
Issued 1/11/2023 APPLICANT
CofO in Progress 12/28/2023 JENNIFER RABUCHIN
CofO Issued 3/18/2024 RUBEN SALAS
Permit Finaled 3/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/15/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/16/2022 COLIN LOREDO
Sewer availability Cleared 8/16/2022 COLIN LOREDO
Low Impact Development Cleared 9/6/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/6/2022 COLIN LOREDO
Construction near power lines Cleared 11/21/2022 RIDWAN HARDY
Construction within easement Cleared 11/21/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 11/25/2022 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2023 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 2/22/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 2/22/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/22/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/8/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 3/8/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 3/8/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Partial Approval JENNIFER RABUCHIN
Insulation 3/10/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/10/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 4/10/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/15/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/15/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Approved JENNIFER RABUCHIN
Gas Test 5/15/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/15/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 5/15/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/15/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/24/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 5/24/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/24/2023 Partial Approval JENNIFER RABUCHIN
Insulation 6/5/2023 Approved JENNIFER RABUCHIN
Shower Pan 6/5/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 6/12/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/12/2023 Approved JENNIFER RABUCHIN
Sewer 7/27/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 7/27/2023 Approved JENNIFER RABUCHIN
Service/Power Release 10/10/2023 Partial Approval JENNIFER RABUCHIN
Final 12/1/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/1/2023 Approved JENNIFER RABUCHIN
Green Building Final 12/1/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 12/1/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 12/1/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/28/2023 Approved JENNIFER RABUCHIN
Final 12/28/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/28/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/28/2023 Approved JENNIFER RABUCHIN
Service/Power Release 12/28/2023 Not Required JENNIFER RABUCHIN