443 N ROCKINGHAM AVE 90049

Certificate Information: 443 N ROCKINGHAM AVE 90049

Application / Permit
22010-20000-03482
Plan Check / Job No.
B22VN10877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'x35' ONE-STORY ACCESSORY DWELLING UNIT W/ ATT. PATIO COVER PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); NFPA-13R THRU-OUT
Permit Issued
Issued on 10/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 SEAN SHAHMIRI
Corrections Issued 8/2/2022 SEAN SHAHMIRI
Quality Review Completed 8/4/2022 OMID HEDAYAT
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 9/19/2022 SEAN SHAHMIRI
Plan Check Approved 9/29/2022 SEAN SHAHMIRI
Issued 10/14/2022 APPLICANT
CofO in Progress 5/2/2025 KEVIN SARGSYAN
Permit Finaled 5/29/2025 RICHARD STEINBACH
CofO Issued 5/29/2025 RICHARD STEINBACH
Permit Finaled 5/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
Watercourse Cleared 8/3/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/4/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/4/2022 HISASHI KOBAYAKAWA
Address approval Cleared 8/31/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 9/21/2022 MATTHEW CRAIG
Low Impact Development Cleared 9/21/2022 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 9/21/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Sky Remodeling Inc; Lic. No.: 955109-B 12439 MAGNOLIA BLVD #245      VALLEY VILLAGE, CA 91607
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/21/2022 No Access for Inspection DAVID FEILER
Deputy Reinf. Concrete 1/26/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/27/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/31/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 2/27/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/3/2023 Partial Approval KEVIN SARGSYAN
Deputy Steel/Welding 3/9/2023 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/24/2023 Not Ready for Inspection KEVIN SARGSYAN
Deputy Reinf. Concrete 3/28/2023 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/29/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/5/2023 Approved KENNETH NAGLE
Deputy Steel/Welding 4/6/2023 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 4/24/2023 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 6/12/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 12/5/2023 Approved KEVIN SARGSYAN
HVAC-Rough 12/6/2023 Approved KEVIN SARGSYAN
Deputy Wood Construction 12/7/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 12/8/2023 Corrections Issued KEVIN SARGSYAN
Shower Pan 1/5/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 1/16/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/18/2024 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 1/18/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/25/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 1/29/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 2/1/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 2/9/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/29/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/4/2024 Conditional Approval ARAM AVEDISIAN
Green Building Rough 3/4/2024 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 3/4/2024 Approved ARAM AVEDISIAN
Insulation 3/7/2024 Corrections Issued KEVIN SARGSYAN
Insulation 3/11/2024 Conditional Approval KEVIN SARGSYAN
Drywall Nailing 3/21/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 2/11/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 2/26/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 2/27/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 2/28/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/5/2025 Approved KEVIN SARGSYAN
HVAC-Final 3/5/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/9/2025 Approved KEVIN SARGSYAN
Final 4/9/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/9/2025 Approved KEVIN SARGSYAN
Green Building Final 4/9/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/9/2025 Not Required KEVIN SARGSYAN
Smoke Detectors 4/9/2025 Approved KEVIN SARGSYAN
Final 4/23/2025 Not Ready for Inspection KEVIN SARGSYAN
Final 5/1/2025 OK to Issue CofO KEVIN SARGSYAN