441 N ROCKINGHAM AVE 90049

Certificate Information: 441 N ROCKINGHAM AVE 90049

Application / Permit
22010-20000-03481
Plan Check / Job No.
B22VN10877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 76' x 150'-5 1/2" TWO-STORY SINGLE FAMILY DWELLING WITH A BASEMENT AND ATT 4-CAR GARAGE AND ATT. JUNIOR ACCESSORY DWELLING UNIT (PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229) AND PATIO COVER; NFPA-13D THRU-13D
Permit Issued
Issued on 10/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 SEAN SHAHMIRI
Corrections Issued 8/2/2022 SEAN SHAHMIRI
Quality Review Completed 8/4/2022 OMID HEDAYAT
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 9/19/2022 SEAN SHAHMIRI
Plan Check Approved 9/29/2022 SEAN SHAHMIRI
Issued 10/14/2022 APPLICANT
CofO in Progress 5/2/2025 KEVIN SARGSYAN
Permit Finaled 5/29/2025 RICHARD STEINBACH
CofO Issued 5/29/2025 RICHARD STEINBACH
Permit Finaled 5/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 8/3/2022 HISASHI KOBAYAKAWA
Watercourse Cleared 8/3/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/4/2022 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 8/17/2022 ADALBERTO VERA
Address approval Cleared 8/31/2022 HISASHI KOBAYAKAWA
Permit Cleared 8/31/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/13/2022 HISASHI KOBAYAKAWA
Low Impact Development Cleared 9/20/2022 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 9/21/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 9/21/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Sky Remodeling Inc; Lic. No.: 955109-B 12439 MAGNOLIA BLVD #245      VALLEY VILLAGE, CA 91607
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/10/2022 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 11/16/2022 Partial Approval JUAN VALENZUELA
Piling/Pier/Caisson 11/16/2022 Corrections Issued JUAN VALENZUELA
Deputy Reinf. Concrete 11/29/2022 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/30/2022 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 12/1/2022 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 12/15/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 12/16/2022 Partial Approval JUAN VALENZUELA
Deputy Shotcrete 1/3/2023 Conditional Approval KEVIN SARGSYAN
Masonry Wall/Backfill 1/5/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 1/6/2023 Conditional Approval CLAYTON GRAHAM
PLUMBING-Rough 2/22/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 2/23/2023 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 2/27/2023 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 3/2/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 3/28/2023 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/4/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/5/2023 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 4/5/2023 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 4/7/2023 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/11/2023 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 4/11/2023 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/12/2023 Corrections Issued KENNETH NAGLE
Reinforced Concrete Frame 4/14/2023 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 4/18/2023 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 5/15/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 6/12/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 8/1/2023 Conditional Approval MICHAEL PELHAM
HVAC-Rough 8/22/2023 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 8/23/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/20/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/28/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 12/5/2023 Approved KEVIN SARGSYAN
HVAC-Rough 12/6/2023 Not Ready for Inspection KEVIN SARGSYAN
Deputy Wood Construction 12/7/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 12/8/2023 Corrections Issued KEVIN SARGSYAN
Shower Pan 1/5/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 1/16/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/17/2024 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 1/17/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/29/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 2/1/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 2/9/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/29/2024 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 3/4/2024 Approved ARAM AVEDISIAN
Green Building Rough 3/4/2024 Approved ARAM AVEDISIAN
Special/Order Compliance 3/4/2024 Corrections Issued ARAM AVEDISIAN
Verify Sprinkler Sign Off 3/4/2024 Approved ARAM AVEDISIAN
Insulation 3/7/2024 Approved KEVIN SARGSYAN
Drywall Nailing 3/18/2024 Corrections Issued KEVIN SARGSYAN
Drywall Nailing 3/22/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 3/22/2024 Partial Approval KEVIN SARGSYAN
Sewer 7/2/2024 Approved KENNETH NAGLE
Gas Test 7/12/2024 Partial Approval KEVIN SARGSYAN
HVAC-Final 8/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Deputy Reinf. Concrete 10/15/2024 Conditional Approval KEVIN SARGSYAN
PLUMBING-Final 2/10/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 2/26/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 2/27/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 2/28/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 3/5/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 3/5/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 3/11/2025 Partial Approval KEVIN SARGSYAN
PLUMBING-Final 3/11/2025 Approved KEVIN SARGSYAN
HVAC-Final 3/12/2025 No Access for Inspection KEVIN SARGSYAN
Service/Power Release 3/14/2025 Approved KENNETH NAGLE
HVAC-Final 3/17/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/19/2025 Approved KEVIN SARGSYAN
Final 4/9/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/9/2025 Approved KEVIN SARGSYAN
Green Building Final 4/9/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 4/9/2025 Approved KEVIN SARGSYAN
Final 4/23/2025 Corrections Issued KEVIN SARGSYAN
Final 5/1/2025 OK to Issue CofO KEVIN SARGSYAN