1776 W 37TH PL 90018
Certificate Information: 1776 W 37TH PL 90018
- Application / Permit
- 22010-20000-03454
- Plan Check / Job No.
- B22VN10827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 43' X 14' THREE STORY SFD WITH ATTACHED 1 CAR GARAGE AND 1 CAR CARPORT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Current Status
- CofO Issued on 12/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | RARES BODEA |
| Corrections Issued | 8/1/2022 | RARES BODEA |
| Quality Review Completed | 8/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/5/2022 | APPLICANT |
| Applicant returned to address corrections | 6/1/2023 | RARES BODEA |
| Plan Check Approved | 7/19/2023 | RARES BODEA |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 12/19/2024 | SABAS ALONSO |
| Permit Finaled | 12/20/2024 | DEROLD HAUFF |
| CofO Issued | 12/20/2024 | DEROLD HAUFF |
| Permit Finaled | 12/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2022 | CELINA MORENO |
| Highway dedication | Cleared | 8/17/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | CELINA MORENO |
| Sewer availability | Cleared | 8/19/2022 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 8/22/2022 | KEVIN ARUCAN |
| Community Plan Implem. Overlay | Cleared | 8/25/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/25/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/26/2022 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 9/1/2022 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 9/9/2022 | LAVEON RIDER |
| Community Plan Implem. Overlay | Cleared | 10/11/2022 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 10/14/2022 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 11/5/2022 | RIDWAN HARDY |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | 4606 WILLIS AVE #307 SHERMAN OAKS, CA 91403 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/23/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/30/2023 | No Access for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/11/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/26/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 2/16/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/19/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 4/22/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/23/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 4/23/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/30/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/30/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/7/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 5/9/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/9/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/17/2024 | Conditional Approval | SABAS ALONSO |
| Insulation | 5/21/2024 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 5/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 5/24/2024 | No Access for Inspection | SABAS ALONSO |
| Drywall Nailing | 5/29/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 5/29/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 7/1/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 7/8/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/10/2024 | Approved | SABAS ALONSO |
| Shower Pan | 7/12/2024 | Approved | BRENDAN MORELLI |
| Sewer | 8/2/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 10/21/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 10/21/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 10/21/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 10/30/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 10/30/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | SABAS ALONSO |
| Final | 12/4/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/4/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 12/4/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 12/4/2024 | Approved | SABAS ALONSO |
| Final | 12/18/2024 | OK to Issue CofO | SABAS ALONSO |