1776 W 37TH PL 90018

Certificate Information: 1776 W 37TH PL 90018

Application / Permit
22010-20000-03454
Plan Check / Job No.
B22VN10827
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 43' X 14' THREE STORY SFD WITH ATTACHED 1 CAR GARAGE AND 1 CAR CARPORT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 12/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 RARES BODEA
Corrections Issued 8/1/2022 RARES BODEA
Quality Review Completed 8/4/2022 STEVEN KIM
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 6/1/2023 RARES BODEA
Plan Check Approved 7/19/2023 RARES BODEA
Issued 7/25/2023 APPLICANT
CofO in Progress 12/19/2024 SABAS ALONSO
Permit Finaled 12/20/2024 DEROLD HAUFF
CofO Issued 12/20/2024 DEROLD HAUFF
Permit Finaled 12/20/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/17/2022 CELINA MORENO
Highway dedication Cleared 8/17/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/19/2022 CELINA MORENO
Sewer availability Cleared 8/19/2022 CELINA MORENO
Community Plan Implem. Overlay Cleared 8/22/2022 KEVIN ARUCAN
Community Plan Implem. Overlay Cleared 8/25/2022 ADALBERTO VERA
Low Impact Development Cleared 8/25/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/26/2022 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 9/1/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 9/9/2022 LAVEON RIDER
Community Plan Implem. Overlay Cleared 10/11/2022 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 10/14/2022 CELINA MORENO
Community Plan Implem. Overlay Cleared 11/5/2022 RIDWAN HARDY

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Gemilyan Karen; Lic. No.: 801955-B 4606 WILLIS AVE #307      SHERMAN OAKS, CA 91403
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/23/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/30/2023 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/11/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 9/26/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Partial Approval SABAS ALONSO
Green Building Rough 11/9/2023 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 11/9/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 2/16/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 4/19/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 4/22/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 4/23/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 4/23/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 4/30/2024 Approved SABAS ALONSO
HVAC-Rough 4/30/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Approved SABAS ALONSO
PLUMBING-Rough 5/7/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/9/2024 Corrections Issued SABAS ALONSO
Green Building Rough 5/9/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 5/9/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/17/2024 Conditional Approval SABAS ALONSO
Insulation 5/21/2024 Conditional Approval JOSH MEISTER
Drywall Nailing 5/24/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/24/2024 No Access for Inspection SABAS ALONSO
Drywall Nailing 5/29/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 5/29/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 7/1/2024 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 7/8/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 7/10/2024 Approved SABAS ALONSO
Shower Pan 7/12/2024 Approved BRENDAN MORELLI
Sewer 8/2/2024 Approved ALEX COLIN
ELECTRICAL-Final 10/21/2024 Corrections Issued SABAS ALONSO
HVAC-Final 10/21/2024 Corrections Issued SABAS ALONSO
PLUMBING-Final 10/21/2024 Approved SABAS ALONSO
ELECTRICAL-Final 10/30/2024 Approved SABAS ALONSO
HVAC-Final 10/30/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/4/2024 Approved SABAS ALONSO
Final 12/4/2024 Corrections Issued SABAS ALONSO
Green Building Final 12/4/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 12/4/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 12/4/2024 Approved SABAS ALONSO
Final 12/18/2024 OK to Issue CofO SABAS ALONSO