8333 N WHITE OAK AVE 91325
Certificate Information: 8333 N WHITE OAK AVE 91325
- Application / Permit
- 22010-20000-03444
- Plan Check / Job No.
- B22VN10794
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | DANIEL YIP |
| Corrections Issued | 7/24/2022 | DANIEL YIP |
| Quality Review Completed | 7/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/23/2022 | DANIEL YIP |
| Plan Check Approved | 12/8/2022 | DANIEL YIP |
| Issued | 12/8/2022 | APPLICANT |
| CofO in Progress | 3/4/2024 | JAVIER RAMOS JR |
| No Progress | 4/3/2024 | DANIEL ORRANTE |
| CofO in Progress | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/30/2024 | RUBEN SALAS |
| CofO Issued | 4/30/2024 | RUBEN SALAS |
| Permit Finaled | 4/30/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/29/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 11/1/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tabirara,, Vernon Nicolas; Lic. No.: C75492 | 17520 DAPHNE AVE TORRANCE, CA 90504 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/27/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/25/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 4/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 4/10/2023 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 4/28/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/26/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/26/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/26/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/26/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/26/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/26/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 6/9/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 6/28/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 6/28/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 12/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 12/6/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/9/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/29/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 2/29/2024 | Approved | JAVIER RAMOS JR |