342-344 E 78TH ST 90003

Certificate Information: 342-344 E 78TH ST 90003

Application / Permit
22010-20000-03442
Plan Check / Job No.
B22VN10791
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New Detached 2-unit ADU PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 2/17/2023
Issuing Office
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 JAD BASMA
Corrections Issued 8/18/2022 JAD BASMA
Quality Review Completed 8/31/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/13/2023 JAD BASMA
Applicant returned to address corrections 2/7/2023 JAD BASMA
Plan Check Approved 2/16/2023 JAD BASMA
Issued 2/17/2023 APPLICANT
CofO in Progress 10/6/2023 MICHAEL LEWIS
Permit Finaled 10/24/2023 DEROLD HAUFF
CofO Issued 10/24/2023 DEROLD HAUFF
Permit Finaled 10/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2022 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 9/14/2022 ADRIAN SANCHEZ
Sewer availability Cleared 9/14/2022 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 10/31/2022 RUEL COLE
Permit Cleared 11/2/2022 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 11/2/2022 ADRIAN SANCHEZ
Trees in Parkway Cleared 2/1/2023 ADALBERTO VERA

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: NA37588       ,
Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/23/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/11/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/11/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 5/30/2023 Approved MICHAEL LEWIS
HVAC-Rough 5/30/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 5/30/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 6/2/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 6/2/2023 Approved STUART CHAPMAN
Wood Frame 6/2/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/13/2023 Approved MICHAEL LEWIS
Insulation 6/20/2023 Approved MICHAEL LEWIS
Shower Pan 6/20/2023 Approved MICHAEL LEWIS
Drywall Nailing 6/27/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 6/27/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 8/24/2023 Approved MICHAEL LEWIS
PLUMBING-Final 8/24/2023 Approved MICHAEL LEWIS
Service/Power Release 10/3/2023 Corrections Issued MICHAEL LEWIS
Final 10/6/2023 OK to Issue CofO MICHAEL LEWIS
Footing/Foundation/Slab 10/6/2023 Approved MICHAEL LEWIS
HVAC-Final 10/6/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 10/6/2023 Approved MICHAEL LEWIS
Smoke Detectors 10/6/2023 Approved MICHAEL LEWIS