12745 W HANOVER ST 90049
Certificate Information: 12745 W HANOVER ST 90049
- Application / Permit
- 22010-20000-03410
- Plan Check / Job No.
- B22VN10689
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 7'-8" x 21'-8" POOL ACCESSORY STRUCTURE WITH A HALF BATHROOM AND AN ATTACHED 17'-8" x 9'-11" OPEN TRELLIS PATIO AND ATTACHED BLOCK WALL. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 7/16/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Applicant returned to address corrections | 9/19/2022 | ROSENDO MEDINA |
| Plan Check Approved | 1/26/2023 | SARKIS HARABEDIAN |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 9/23/2025 | HERBERT GIRON |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/10/2022 | ASHLEY RODARTE |
| Roof/Waste drainage to street | Cleared | 8/29/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | JENSON LEE |
| Specific Plan | Cleared | 9/6/2022 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 9/19/2022 | ROSENDO MEDINA |
Contact Information
| Architect | Yotnegparian,, Alain Levon; Lic. No.: C26374 | 11541 DONA PEPITA PLACE STUDIO CITY, CA 91604 |
| Contractor | Rattigan Construction; Lic. No.: 760004-B | 11549 DILLING ST STUDIO CITY, CA 91604 |
| Engineer | Koh,, William Kim; Lic. No.: S3473 | 5695 STARWOOD CT WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 5/17/2023 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/23/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Gas Test | 5/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 6/21/2023 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Reinf. Masonry | 7/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Masonry Wall/Backfill | 7/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Masonry Wall/Backfill | 7/31/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/7/2023 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/7/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/16/2023 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/26/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/8/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 7/25/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 7/31/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/2/2025 | Conditional Approval | MICHAEL ALLEN |
| Final | 9/2/2025 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 9/2/2025 | Approved | MICHAEL ALLEN |
| Green Building Final | 9/2/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 9/2/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 9/2/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 9/16/2025 | Approved | HERBERT GIRON |
| Final | 9/16/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 9/16/2025 | Approved | HERBERT GIRON |
| PLUMBING-Final | 9/16/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | HERBERT GIRON |
| Final | 9/23/2025 | OK to Issue CofO | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/23/2025 | Approved | HERBERT GIRON |