13049 N BORDEN AVE 91342
Certificate Information: 13049 N BORDEN AVE 91342
- Application / Permit
- 22010-20000-03371
- Plan Check / Job No.
- B22VN10575
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert (E) Gar/Storg to ADU per ordinance.
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/18/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/2/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/3/2022 | FARSHAD ALIMOHAMADI |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 8/28/2024 | RAUL OLAGI |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/29/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | ROMAN GUTIERREZ |
| Address approval | Cleared | 8/22/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/1/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/21/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 5/21/2024 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 5/21/2024 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/23/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/23/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/23/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 5/28/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/28/2024 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 6/3/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/3/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/6/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/6/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | KEVIN BERBERYAN |
| Final | 8/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 8/1/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 8/1/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 8/1/2024 | Approved | KEVIN BERBERYAN |
| Final | 8/27/2024 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 8/27/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | RAUL OLAGI |