20338 W CANTARA ST 91306
Certificate Information: 20338 W CANTARA ST 91306
- Application / Permit
- 22010-20000-03367
- Plan Check / Job No.
- B22VN10572
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY DETACHED ACCESSORY DWELLING UNIT (22'-0"x26'-8"), 1120 SQFT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 2/24/2024
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | PETER MOSESIAN |
| Corrections Issued | 7/23/2022 | PETER MOSESIAN |
| Quality Review Completed | 7/29/2022 | OMID HEDAYAT |
| Plan Check Approved | 2/13/2024 | PETER MOSESIAN |
| Issued | 2/24/2024 | APPLICANT |
| CofO in Progress | 1/13/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/6/2025 | JOHN JANSON |
| CofO Issued | 2/6/2025 | JOHN JANSON |
| Permit Finaled | 2/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/10/2023 | GILBERT URREA |
| Address approval | Cleared | 3/22/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/4/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/30/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/26/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 1/30/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/7/2024 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 3/13/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 4/10/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/25/2024 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/1/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/1/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/14/2024 | Corrections Issued | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/16/2024 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 5/21/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 5/24/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/24/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/20/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 7/31/2024 | Approved | ARUTYUN MADATYAN |
| Pre-Inspection | 8/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 9/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 9/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 9/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 9/30/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | ARUTYUN MADATYAN |
| Final | 10/29/2024 | Corrections Issued | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 10/29/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 10/29/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | ARUTYUN MADATYAN |
| Final | 1/13/2025 | OK to Issue CofO | ALEXANDER HANDY |