5114 N SHEARIN AVE 90041

Certificate Information: 5114 N SHEARIN AVE 90041

Application / Permit
22010-20000-03335
Plan Check / Job No.
B22VN10454
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 39' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 RAPHAEL ROSAS
Corrections Issued 8/8/2022 RAPHAEL ROSAS
Quality Review Completed 8/12/2022 STEVEN KIM
Building Plans Picked Up 8/15/2022 APPLICANT
Applicant returned to address corrections 11/3/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/1/2023 RAPHAEL ROSAS
Plan Check Approved 4/6/2023 RAPHAEL ROSAS
Issued 4/28/2023 APPLICANT
CofO in Progress 11/13/2024 ROY SPAULDING
No Progress 11/23/2024 DEROLD HAUFF
CofO in Progress 11/23/2024 DEROLD HAUFF
Permit Finaled 12/3/2024 DEROLD HAUFF
CofO Issued 12/3/2024 DEROLD HAUFF
Permit Finaled 12/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/8/2022 CINDY QI
Low Impact Development Cleared 10/31/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/31/2022 CINDY QI
Sewer availability Cleared 11/22/2022 CINDY QI
Construction near power lines Cleared 2/6/2023 NADER ISKANDER
GPI Written Notices Cleared 4/6/2023 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 4/6/2023 RAPHAEL ROSAS

Contact Information

Contractor Opus Builders Inc; Lic. No.: 1059646-B 5244 VINELAND AVENUE      NORTH HOLLYWOOD, CA 91601
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/7/2023 Approved CRAIG VAUGHAN
Underground Mechanical 6/7/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 6/16/2023 Approved BRIAN SULLIVAN
Deputy Reinf. Concrete 6/22/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 10/27/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 11/6/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/6/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 11/6/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/6/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/6/2023 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/6/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/7/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/7/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/7/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 11/9/2023 Approved CRAIG VAUGHAN
Insulation 11/20/2023 Approved ROY SPAULDING
Drywall Nailing 11/29/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/12/2023 Approved CRAIG VAUGHAN
Shower Pan 12/12/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 10/29/2024 Not Ready for Inspection ROY SPAULDING
Final 10/30/2024 Not Ready for Inspection ROY SPAULDING
Green Building Final 10/30/2024 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready ROY SPAULDING
Service/Power Release 10/30/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 10/30/2024 Not Ready for Inspection ROY SPAULDING
Final 11/6/2024 OK to Issue CofO ROY SPAULDING
Green Building Final 11/6/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 11/6/2024 Approved ROY SPAULDING
Smoke Detectors 11/6/2024 Approved ROY SPAULDING