8157 N VARNA AVE 91402
Certificate Information: 8157 N VARNA AVE 91402
- Application / Permit
- 22010-20000-03328
- Plan Check / Job No.
- B22VN10437
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | CARLOS MONTES |
| Corrections Issued | 8/8/2022 | CARLOS MONTES |
| Quality Review Completed | 8/11/2022 | KEN GILL |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| Applicant returned to address corrections | 3/24/2023 | CARLOS MONTES |
| Plan Check Approved | 3/30/2023 | CARLOS MONTES |
| Issued | 3/30/2023 | APPLICANT |
| CofO in Progress | 4/29/2025 | VINCENT HANLEY |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
| CofO Issued | 5/22/2025 | RUBEN SALAS |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/26/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/3/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/1/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 4/17/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/14/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | DAVID MATSON |
| Wood Frame | 7/25/2023 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/30/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 8/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 8/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/11/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/11/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 10/4/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/24/2023 | Conditional Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/19/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 12/19/2023 | Partial Approval | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/22/2024 | Partial Approval | GREGG CUMMINGS |
| Insulation | 3/14/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 3/19/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/3/2024 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 4/3/2024 | Approved | GREGG CUMMINGS |
| Final | 1/3/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/3/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 1/3/2025 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 1/3/2025 | Approved | VINCENT HANLEY |
| Final | 3/14/2025 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 3/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 4/28/2025 | Approved | VINCENT HANLEY |
| Final | 4/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 4/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/28/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 4/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/6/2025 | Approved | VINCENT HANLEY |