6473 N LONGRIDGE AVE 91401

Certificate Information: 6473 N LONGRIDGE AVE 91401

Application / Permit
22010-20000-03322
Plan Check / Job No.
B22VN10402
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 20 ' x 32'-8" TWO-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/23/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/10/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/18/2022 OMID HEDAYAT
Building Plans Picked Up 8/23/2022 APPLICANT
Plan Check Approved 1/23/2023 SEWADA ZADOORAN MILAGARDI
Issued 1/23/2023 APPLICANT
CofO in Progress 2/8/2024 JOSE AVILA
No Progress 3/2/2024 JUAN VALENZUELA
CofO in Progress 3/2/2024 JUAN VALENZUELA
Permit Finaled 4/15/2024 RUBEN SALAS
CofO Issued 4/15/2024 RUBEN SALAS
Permit Finaled 4/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/4/2022 MEGAN GODINEZ
Sewer availability Cleared 10/14/2022 MEGAN GODINEZ
Construction near power lines Cleared 10/22/2022 WALTER RAMIREZ
Construction within easement Cleared 10/22/2022 WALTER RAMIREZ
Low Impact Development Cleared 12/20/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 12/22/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 1/20/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 1/20/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 1/20/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 1/20/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/15/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 2/27/2023 Approved MICHEL ABAJAN
Deputy Wood Construction 4/28/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 5/2/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/2/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval KIRK SANDERS
Green Building Rough 5/2/2023 Approved KIRK SANDERS
HVAC-Rough 5/2/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/2/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/2/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Approved KIRK SANDERS
Underground Mechanical 5/9/2023 Approved KIRK SANDERS
Wood Frame 5/9/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 5/16/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 5/16/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 5/16/2023 Partial Approval KIRK SANDERS
Verify Sprinkler Sign Off 5/16/2023 Approved KIRK SANDERS
Insulation 5/22/2023 Approved JUAN VALENZUELA
Drywall Nailing 5/30/2023 Approved JUAN VALENZUELA
Shower Pan 6/9/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/7/2023 Approved KIRK SANDERS
Final 11/22/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 11/22/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/22/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 11/22/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/22/2023 Corrections Issued MISAEL ESPARZA
Final 12/20/2023 Not Ready for Inspection JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved JOHN COLEMAN
Service/Power Release 12/20/2023 Conditional Approval JOHN COLEMAN
Smoke Detectors 12/20/2023 Approved JOHN COLEMAN
Final 1/16/2024 Partial Approval JOSE AVILA
Service/Power Release 1/16/2024 Approved JOSE AVILA
Final 2/8/2024 OK to Issue CofO JOSE AVILA