12755 W OSBORNE ST 91331
Certificate Information: 12755 W OSBORNE ST 91331
- Application / Permit
- 22010-20000-03316
- Plan Check / Job No.
- B22VN10387
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING TO ADD A BEDROOM AND 16'-5" X 15'-4" PATIO COVER
- Permit Issued
- Issued on 11/4/2022
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | DANIEL YIP |
| Corrections Issued | 7/14/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/31/2022 | DANIEL YIP |
| Applicant returned to address corrections | 10/21/2022 | DANIEL YIP |
| Plan Check Approved | 11/3/2022 | DANIEL YIP |
| Issued | 11/4/2022 | APPLICANT |
| CofO in Progress | 4/14/2025 | MICHEL ABAJAN |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| CofO Issued | 4/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/7/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/12/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | COLIN LOREDO |
| Clean Up Green Up | Cleared | 10/20/2022 | RUBEN VASQUEZ |
| Zoning Information File | Cleared | 10/27/2022 | JOHN FRANCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ahmad,, Rais; Lic. No.: C74446 | 17726 HALSTED ST A NORTHRIDGE, CA 91325 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/21/2023 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 2/21/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/21/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 5/23/2024 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | JOHN COLEMAN |
| Insulation | 5/28/2024 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/7/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/7/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/7/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 10/7/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/7/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/29/2024 | Approved | MICHEL ABAJAN |
| Insulation | 11/20/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/20/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/21/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/29/2025 | Approved | MICHEL ABAJAN |
| Final | 1/29/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/29/2025 | Approved | MICHEL ABAJAN |
| Green Building Final | 1/29/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/29/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/29/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/29/2025 | Approved | MICHEL ABAJAN |
| Final | 4/11/2025 | OK to Issue CofO | MICHEL ABAJAN |