12755 W OSBORNE ST 91331

Certificate Information: 12755 W OSBORNE ST 91331

Application / Permit
22010-20000-03316
Plan Check / Job No.
B22VN10387
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING TO ADD A BEDROOM AND 16'-5" X 15'-4" PATIO COVER
Permit Issued
Issued on 11/4/2022
Issuing Office
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/13/2022 DANIEL YIP
Corrections Issued 7/14/2022 DANIEL YIP
Applicant returned to address corrections 8/31/2022 DANIEL YIP
Applicant returned to address corrections 10/21/2022 DANIEL YIP
Plan Check Approved 11/3/2022 DANIEL YIP
Issued 11/4/2022 APPLICANT
CofO in Progress 4/14/2025 MICHEL ABAJAN
Permit Finaled 4/22/2025 RUBEN SALAS
Permit Finaled 4/22/2025 RUBEN SALAS
CofO Issued 4/22/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/7/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 10/7/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 10/12/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/13/2022 COLIN LOREDO
Clean Up Green Up Cleared 10/20/2022 RUBEN VASQUEZ
Zoning Information File Cleared 10/27/2022 JOHN FRANCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ahmad,, Rais; Lic. No.: C74446 17726 HALSTED ST A      NORTHRIDGE, CA 91325

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2023 Partial Inspection MICHEL ABAJAN
METHANE-Barrier 2/21/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 2/21/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/23/2024 Partial Approval MICHEL ABAJAN
Pre-Inspection 5/23/2024 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 5/28/2024 Corrections Issued JOHN COLEMAN
Insulation 5/28/2024 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/7/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 10/7/2024 Approved MICHEL ABAJAN
Green Building Rough 10/7/2024 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 10/7/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 10/7/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/29/2024 Approved MICHEL ABAJAN
Green Building Rough 10/29/2024 Approved MICHEL ABAJAN
Insulation 11/20/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/20/2024 Approved MICHEL ABAJAN
Drywall Nailing 11/21/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/29/2025 Approved MICHEL ABAJAN
Final 1/29/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 1/29/2025 Approved MICHEL ABAJAN
Green Building Final 1/29/2025 Approved MICHEL ABAJAN
HVAC-Final 1/29/2025 Approved MICHEL ABAJAN
PLUMBING-Final 1/29/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/29/2025 Approved MICHEL ABAJAN
Final 4/11/2025 OK to Issue CofO MICHEL ABAJAN