13649 W SUNBURST ST 91331
Certificate Information: 13649 W SUNBURST ST 91331
- Application / Permit
- 22010-20000-03298
- Plan Check / Job No.
- B22VN10381
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Propose convert (E) garage in to ADU plus addition PER LAMC 12.22 A.33 (c) AND (d). see comments.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2022 | DANIEL SANJUAN |
| Corrections Issued | 7/12/2022 | DANIEL SANJUAN |
| Plan Check Approved | 8/30/2022 | DANIEL SANJUAN |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 3/3/2023 | GREGG CUMMINGS |
| Permit Finaled | 3/17/2023 | MICHAEL SMITH |
| CofO Issued | 3/17/2023 | MICHAEL SMITH |
| Permit Finaled | 3/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 7/14/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/14/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 10/7/2022 | Partial Approval | WILLIAM WREN |
| Sewer | 10/7/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 10/7/2022 | Approved | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 10/18/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 10/18/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/19/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/7/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/7/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 11/14/2022 | Approved | WILLIAM WREN |
| HVAC-Rough | 11/14/2022 | Approved | WILLIAM WREN |
| Insulation | 11/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 12/13/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/13/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/16/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/16/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/2/2023 | Approved | GREGG CUMMINGS |
| Final | 3/2/2023 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 3/2/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 3/2/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 3/2/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/2/2023 | Approved | GREGG CUMMINGS |