7500 N GLENOAKS BLVD 91504
Certificate Information: 7500 N GLENOAKS BLVD 91504
- Application / Permit
- 22010-20000-03278
- Plan Check / Job No.
- B22VN10274
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NEW SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | KEVIN MORALES |
| Corrections Issued | 7/12/2022 | KEVIN MORALES |
| Quality Review Completed | 7/13/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/2/2022 | KEVIN MORALES |
| Plan Check Approved | 9/28/2022 | KEVIN MORALES |
| Issued | 10/3/2022 | APPLICANT |
| CofO in Progress | 7/23/2024 | DAVID ANDERSON |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Watercourse | Cleared | 7/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/27/2022 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 8/8/2022 | BRENNEN OBETO |
| "Q" conditions | Cleared | 8/9/2022 | BRENNEN OBETO |
| Address approval | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/23/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 8/29/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 9/7/2022 | KIRK LINKLATER |
| Highway dedication | Cleared | 9/16/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Najarian Building And Development; Lic. No.: 1016845-B | 2524 MARY STREET MONTROSE, CA 91020 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/13/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Partial Approval | DAVID ANDERSON |
| Pre-Inspection | 2/7/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 2/8/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 2/17/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 3/7/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 3/7/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/7/2023 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 3/14/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Drilled-In Anchors | 3/15/2023 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 3/15/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 3/21/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 3/21/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/3/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/5/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/5/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/12/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 8/3/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 8/3/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 10/23/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 12/1/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 1/29/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 5/22/2024 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/22/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 5/22/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | DAVID ANDERSON |
| Final | 5/24/2024 | Corrections Issued | DAVID ANDERSON |
| MERV13>=Final | 5/24/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 5/24/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 5/24/2024 | Order to Comply Issued | DAVID ANDERSON |
| Final | 7/5/2024 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/5/2024 | Approved | DAVID ANDERSON |
| Final | 7/11/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 7/11/2024 | Approved | DAVID ANDERSON |
| Final | 7/23/2024 | OK to Issue CofO | DAVID ANDERSON |