2521 S LUCERNE AVE 90016
Certificate Information: 2521 S LUCERNE AVE 90016
- Application / Permit
- 22010-20000-03266
- Plan Check / Job No.
- B22VN10220
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT ( 12'-10"X24'-4" ) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Valley
- Current Status
- Issued on 11/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/16/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | MOHAMMAD ESMAILI |
| Issued | 11/8/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/28/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 9/16/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Corrections Issued | CALEB MEISTER |
| Footing/Foundation/Slab | 12/29/2022 | Corrections Issued | CALEB MEISTER |
| Footing/Foundation/Slab | 1/6/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/3/2023 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 3/9/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 3/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 3/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 3/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 3/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 3/9/2023 | Partial Approval | CALEB MEISTER |
| Verify Sprinkler Sign Off | 3/9/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 3/13/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 3/13/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 3/22/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 3/22/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/22/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 3/22/2023 | Approved | CALEB MEISTER |
| Structural Steel Frame | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 3/30/2023 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 3/30/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/11/2023 | Corrections Issued | CALEB MEISTER |
| Wood Frame | 4/11/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 4/17/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 5/17/2023 | Approved | CALEB MEISTER |
| Sewer | 6/15/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 6/22/2023 | Approved | CALEB MEISTER |
| Gas Test | 7/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/13/2024 | Approved | JUSTIN HAWLEY |
| Final | 2/13/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 2/13/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 2/13/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 2/13/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 3/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/27/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 3/27/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/27/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 3/27/2024 | Approved | JUSTIN HAWLEY |
| Final | 5/26/2026 | Corrections Issued | JUSTIN HAWLEY |