10537 N VARIEL AVE 91311
Certificate Information: 10537 N VARIEL AVE 91311
- Application / Permit
- 22010-20000-03257
- Plan Check / Job No.
- B22VN10203
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-11" x 31'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEER. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 7/16/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/13/2022 | LUIS RINCON |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 7/28/2025 | DAVID SCANTLIN |
| CofO Issued | 8/20/2025 | JOHN JANSON |
| Permit Finaled | 8/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/20/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 9/30/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 12/7/2022 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 12/7/2022 | SARKIS HARABEDIAN |
| Roof/Waste drainage to street | Cleared | 12/9/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chu,, Tien Manh; Lic. No.: C72324 | 9542 PACIFIC AVE ANAHEIM, CA 92804 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2023 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 10/31/2023 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/7/2023 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 11/8/2023 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/14/2023 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/29/2023 | No Access for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/30/2023 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/22/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/22/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/22/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/22/2023 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/22/2023 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/22/2023 | Approved | JOHN KIDWELL |
| Insulation | 12/28/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/4/2024 | Approved | HENRY KIM |
| Underground Mechanical | 1/26/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/20/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 4/4/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 4/4/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Service/Power Release | 4/4/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Smoke Detectors | 4/4/2024 | Approved | JOHN KIDWELL |
| Final | 6/28/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 7/9/2024 | Approved | DAVID SCANTLIN |
| Final | 7/9/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 8/2/2024 | Approved | DAVID SCANTLIN |
| Final | 2/6/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Final | 7/25/2025 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | DAVID SCANTLIN |