4638 N PLACIDIA AVE 91602

Certificate Information: 4638 N PLACIDIA AVE 91602

Application / Permit
22010-20000-03227
Plan Check / Job No.
B22VN10101
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH ATTACHED GARAGE AND PATIO COVER (2-STORY)
Permit Issued
Issued on 10/26/2023
Issuing Office
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 CARLOS MONTES
Corrections Issued 8/4/2022 CARLOS MONTES
Quality Review Completed 8/4/2022 GARO TELMI
Applicant returned to address corrections 7/21/2023 CARLOS MONTES
Plan Check Approved 10/5/2023 CARLOS MONTES
Issued 10/26/2023 APPLICANT
CofO in Progress 3/5/2026 GAREN HAYRAPETYAN
CofO Issued 3/19/2026 RUBEN SALAS
Permit Finaled 3/19/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/2/2022 MEGAN GODINEZ
Permit Cleared 9/2/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 MEGAN GODINEZ
Sewer availability Cleared 9/7/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 11/19/2022 GILBERT URREA
Trees in Parkway Cleared 8/21/2023 ADALBERTO VERA
Low Impact Development Cleared 9/15/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 9/22/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/7/2023 Not Ready for Inspection JOHN HAYES
Underground Mechanical 12/7/2023 Corrections Issued JOHN HAYES
Underground Mechanical 12/12/2023 Partial Approval MISAEL ESPARZA
Underground Mechanical 12/14/2023 Partial Approval JOHN HAYES
Underground Mechanical 12/15/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/9/2024 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/9/2024 Corrections Issued JOHN HAYES
Reinforced Concrete Frame 1/9/2024 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/10/2024 Approved MISAEL ESPARZA
Reinforced Concrete Frame 1/10/2024 Partial Inspection MISAEL ESPARZA
Deputy Reinf. Concrete 1/11/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 2/8/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 4/3/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 4/3/2024 Conditional Approval ROBERT GOLD
Deputy Reinf. Concrete 4/26/2024 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 4/26/2024 Conditional Approval ROBERT GOLD
Drywall Nailing 5/3/2024 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval JOHN COLEMAN
Green Building Rough 5/3/2024 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 6/6/2024 Corrections Issued JOSE AVILA
Deputy Steel/Welding 6/10/2024 Conditional Approval JUAN VALENZUELA
HVAC-Rough 6/11/2024 Corrections Issued JOSE AVILA
Deputy Steel/Welding 6/21/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/25/2024 Corrections Issued JOSE AVILA
HVAC-Rough 6/27/2024 Approved JOSE AVILA
ELECTRICAL-Rough 6/28/2024 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 7/8/2024 Corrections Issued JOSE AVILA
Green Building Rough 7/8/2024 Approved JOSE AVILA
Interior/Exterior Lathing 7/8/2024 Approved JOSE AVILA
MERV13>=Rough 7/8/2024 Partial Approval JOSE AVILA
Verify Sprinkler Sign Off 7/8/2024 Approved JOSE AVILA
Shower Pan 7/12/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 7/15/2024 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 7/19/2024 Conditional Approval JOSE AVILA
Deputy Wood Construction 8/20/2024 Conditional Approval JUAN VALENZUELA
MERV13>=Rough 8/21/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 9/9/2024 Approved JOSE AVILA
Deputy Wood Construction 9/9/2024 Conditional Approval JUAN VALENZUELA
Insulation 9/16/2024 Approved JOSE AVILA
Drywall Nailing 9/26/2024 Approved JOSE AVILA
Interior/Exterior Lathing 10/16/2024 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 10/22/2024 Approved JOSE AVILA
ELECTRICAL-Rough 12/27/2024 Partial Approval JOSE AVILA
Underground Mechanical 12/27/2024 Partial Approval JOSE AVILA
Underground Mechanical 1/13/2025 Partial Approval JOSE AVILA
Gas Test 4/7/2025 Approved JOSE AVILA
ELECTRICAL-Rough 6/9/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 12/29/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 1/20/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/23/2026 Approved JOSE AVILA
Green Building Final 2/11/2026 Corrections Issued JAVIER RAMOS JR
HVAC-Final 2/11/2026 Partial Approval JAVIER RAMOS JR
MERV13>=Final 2/11/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 2/11/2026 Approved JAVIER RAMOS JR
Final 3/5/2026 OK to Issue CofO GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/5/2026 Approved GAREN HAYRAPETYAN
Green Building Final 3/5/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 3/5/2026 Approved GAREN HAYRAPETYAN
Smoke Detectors 3/5/2026 Approved GAREN HAYRAPETYAN