7718 N JORDAN AVE 91304
Certificate Information: 7718 N JORDAN AVE 91304
- Application / Permit
- 22010-20000-03214
- Plan Check / Job No.
- B22VN10013
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 33'-6" X 20' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING NFPA 13D REQ'D THROUGHOUT
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/5/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/15/2022 | APPLICANT |
| Applicant returned to address corrections | 11/4/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/22/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 8/15/2024 | ALEXANDER HANDY |
| Permit Finaled | 8/30/2024 | JOHN JANSON |
| CofO Issued | 8/30/2024 | JOHN JANSON |
| Permit Finaled | 8/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/30/2022 | DAGOVERTO GUERRERO |
| Tract Map conditions | Cleared | 9/1/2022 | ASHLEY RODARTE |
| Low Impact Development | Cleared | 9/23/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/3/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | No Access for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/11/2023 | No Access for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 8/11/2023 | No Access for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 8/16/2023 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/15/2023 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/15/2023 | Approved | ALEXANDER HANDY |
| Gas Test | 11/15/2023 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 11/15/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 11/15/2023 | Approved | ALEXANDER HANDY |
| METHANE-Rough | 11/15/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 11/15/2023 | Corrections Issued | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 11/15/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/29/2023 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 11/29/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 11/29/2023 | Approved | ALEXANDER HANDY |
| Insulation | 12/11/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/11/2023 | Partial Approval | ALEXANDER HANDY |
| Insulation | 12/19/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 1/3/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/18/2024 | Approved | ALEXANDER HANDY |
| Final | 7/18/2024 | Corrections Issued | ALEXANDER HANDY |
| Gas Test | 7/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 7/18/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 7/18/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 7/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 7/18/2024 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 7/18/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 8/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 8/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 8/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 8/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | ALEXANDER HANDY |
| Final | 8/14/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Gas Test | 8/14/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/14/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 8/14/2024 | Approved | ALEXANDER HANDY |