22863 W SATICOY ST 91304
Certificate Information: 22863 W SATICOY ST 91304
- Application / Permit
- 22010-20000-03207
- Plan Check / Job No.
- B22VN09997
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 29' X 37' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC SEC. 12.22 A.33(c), (d) AND (g). WORK DONE PER WFPP.
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | PINANK PATEL |
| Corrections Issued | 7/2/2022 | PINANK PATEL |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Plan Check Approved | 11/3/2022 | MIROOSH KHACHATOORIAN |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 10/16/2023 | JEFFREY HARTLINE |
| Permit Finaled | 12/11/2023 | JOHN JANSON |
| CofO Issued | 12/11/2023 | JOHN JANSON |
| Permit Finaled | 12/11/2023 | JOHN JANSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/13/2022 | RUEL COLE |
| Hold | Cleared | 8/16/2022 | PRISCILLA RUIZ |
| Low Impact Development | Cleared | 10/26/2022 | DEBORA LEITE |
| Address approval | Cleared | 11/1/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/1/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/29/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/13/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 3/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 3/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/11/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/11/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/20/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/20/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 4/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 4/21/2023 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/21/2023 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/21/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/1/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/1/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 5/1/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/8/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/11/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 7/10/2023 | Approved | HORACE FULTZ |
| Final | 7/10/2023 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 7/10/2023 | Approved | HORACE FULTZ |
| HVAC-Final | 7/10/2023 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Final | 7/10/2023 | Approved | HORACE FULTZ |
| Pre-Inspection | 7/10/2023 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | HORACE FULTZ |
| Service/Power Release | 7/10/2023 | Approved | HORACE FULTZ |
| Smoke Detectors | 7/10/2023 | Approved | HORACE FULTZ |
| HVAC-Final | 7/13/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 7/13/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 10/13/2023 | OK to Issue CofO | JEFFREY HARTLINE |
| Special/Order Compliance | 11/2/2023 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/4/2023 | Approved | JEFFREY HARTLINE |