22737 W ANGEL LANE 91304

Certificate Information: 22737 W ANGEL LANE 91304

Application / Permit
22010-20000-03206
Plan Check / Job No.
B22VN09980
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'-0" x 27'-0" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) (NFPA-13D FIRE SPRINKLERS REQUIRED). WORK DONE PER WFPP.
Permit Issued
Issued on 3/9/2023
Issuing Office
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 JEROME MAGAT PALMA
Corrections Issued 7/2/2022 JEROME MAGAT PALMA
Building Plans Picked Up 7/5/2022 APPLICANT
Applicant returned to address corrections 2/24/2023 DANIEL ABRAMYAN
Plan Check Approved 3/9/2023 MIROOSH KHACHATOORIAN
Issued 3/9/2023 APPLICANT
CofO in Progress 4/19/2024 JEFFREY HARTLINE
CofO Issued 4/29/2024 JOHN JANSON
Permit Finaled 4/29/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/7/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 7/7/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 7/7/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 7/7/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 7/7/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 7/7/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 7/7/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/7/2022 JOSE DUARTE-DIAZ
ZA Case Cleared 7/7/2022 NELSON RODRIGUEZ
"Q" conditions Cleared 7/8/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 7/8/2022 NELSON RODRIGUEZ
Construction near power lines Cleared 1/30/2023 WALTER RAMIREZ
Low Impact Development Cleared 2/6/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/7/2023 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 2/9/2023 MANUEL TEJADA
GPI Written Notices Cleared 2/24/2023 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2023 Not Ready for Inspection HORACE FULTZ
Underground Mechanical 5/24/2023 Approved HORACE FULTZ
Excavation/Setback/Form/Re-Bar 5/30/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/30/2023 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/23/2023 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 7/6/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/6/2023 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 7/6/2023 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 7/6/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/6/2023 Approved CHRIS CHRISTENSEN
Underground Mechanical 7/6/2023 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 7/6/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/26/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 7/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 7/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/2/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 8/2/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/2/2023 Partial Approval CHRIS CHRISTENSEN
Shower Pan 8/2/2023 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 8/2/2023 Approved CHRIS CHRISTENSEN
Insulation 8/17/2023 Approved JUSTIN HAWLEY
Drywall Nailing 8/23/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/23/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/29/2023 Approved CHRIS CHRISTENSEN
Final 11/29/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/29/2023 Approved CHRIS CHRISTENSEN
Green Building Final 11/29/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 11/29/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 11/29/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 11/29/2023 Approved CHRIS CHRISTENSEN
Final 1/22/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 1/22/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 1/22/2024 Approved CHRIS CHRISTENSEN
Pre-Inspection 1/22/2024 Approved CHRIS CHRISTENSEN
Service/Power Release 1/22/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Final 3/28/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 3/28/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Service/Power Release 3/28/2024 Not Required CHRIS CHRISTENSEN
Final 4/19/2024 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 4/19/2024 Approved JEFFREY HARTLINE