22737 W ANGEL LANE 91304
Certificate Information: 22737 W ANGEL LANE 91304
- Application / Permit
- 22010-20000-03206
- Plan Check / Job No.
- B22VN09980
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37'-0" x 27'-0" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) (NFPA-13D FIRE SPRINKLERS REQUIRED). WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 7/2/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/5/2022 | APPLICANT |
| Applicant returned to address corrections | 2/24/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 3/9/2023 | MIROOSH KHACHATOORIAN |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 4/19/2024 | JEFFREY HARTLINE |
| CofO Issued | 4/29/2024 | JOHN JANSON |
| Permit Finaled | 4/29/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 7/7/2022 | NELSON RODRIGUEZ |
| "Q" conditions | Cleared | 7/8/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 7/8/2022 | NELSON RODRIGUEZ |
| Construction near power lines | Cleared | 1/30/2023 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 2/6/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 2/9/2023 | MANUEL TEJADA |
| GPI Written Notices | Cleared | 2/24/2023 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Not Ready for Inspection | HORACE FULTZ |
| Underground Mechanical | 5/24/2023 | Approved | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/30/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/23/2023 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/6/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/6/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/6/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/6/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/6/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/6/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/6/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/26/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 8/23/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/23/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/29/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 11/29/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/29/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/29/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/29/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 11/29/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/29/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 1/22/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 1/22/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 1/22/2024 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 1/22/2024 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 1/22/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 3/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 3/28/2024 | Not Required | CHRIS CHRISTENSEN |
| Final | 4/19/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 4/19/2024 | Approved | JEFFREY HARTLINE |