18653 W MALDEN ST 91324

Certificate Information: 18653 W MALDEN ST 91324

Application / Permit
22010-20000-03179
Plan Check / Job No.
B22VN09906
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLan Addition of 2-story Accessory Dwelling Unit to existing garage.
Permit Issued
Issued on 3/23/2023
Issuing Office
Current Status
CofO Issued on 10/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 2/8/2023 LAWRENCE QUIRANTE
Corrections Issued 2/9/2023 JOSEPH RAFOLS
Applicant returned to address corrections 3/8/2023 LAWRENCE QUIRANTE
Plan Check Approved 3/23/2023 JOE VO
Issued 3/23/2023 APPLICANT
CofO in Progress 10/2/2023 DAVID SCANTLIN
Permit Finaled 10/6/2023 JOHN JANSON
CofO Issued 10/6/2023 JOHN JANSON
Permit Finaled 10/6/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/16/2023 MATTHEW MAHLEBASHIAN
Construction near power lines Cleared 2/21/2023 WALTER RAMIREZ
Stormwater Pollution Mitigatn Cleared 3/1/2023 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 3/3/2023 MATTHEW MAHLEBASHIAN
Roof/Waste drainage to street Cleared 3/3/2023 MATTHEW MAHLEBASHIAN
Sewer availability Cleared 3/3/2023 MATTHEW MAHLEBASHIAN

Contact Information

Contractor S M Development Company Inc; Lic. No.: 450270-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2023 Approved KRISTEN CAUSEY
PLUMBING-Rough 3/31/2023 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval DAVID SCANTLIN
Special/Order Compliance 4/17/2023 Partial Inspection MORRIS JACKSON
Deputy Wood Construction 5/10/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 5/12/2023 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 5/12/2023 Approved JOHN KIDWELL
Green Building Rough 5/12/2023 Partial Inspection JOHN KIDWELL
PLUMBING-Rough 5/12/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/18/2023 Partial Approval JOHN KIDWELL
Green Building Rough 5/18/2023 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 5/23/2023 Approved JOHN KIDWELL
Green Building Rough 5/23/2023 Approved JOHN KIDWELL
Sewer 6/6/2023 Approved JOHN KIDWELL
Underground Mechanical 6/6/2023 Approved JOHN KIDWELL
Insulation 6/21/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/21/2023 Partial Approval JOHN KIDWELL
Drywall Nailing 7/5/2023 Approved JOHN KIDWELL
Final 9/5/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 9/5/2023 Approved JOHN KIDWELL
Green Building Final 9/5/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 9/5/2023 Approved JOHN KIDWELL
Final 10/2/2023 OK to Issue CofO DAVID SCANTLIN