18653 W MALDEN ST 91324
Certificate Information: 18653 W MALDEN ST 91324
- Application / Permit
- 22010-20000-03179
- Plan Check / Job No.
- B22VN09906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLan Addition of 2-story Accessory Dwelling Unit to existing garage.
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/9/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/8/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/23/2023 | JOE VO |
| Issued | 3/23/2023 | APPLICANT |
| CofO in Progress | 10/2/2023 | DAVID SCANTLIN |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
| CofO Issued | 10/6/2023 | JOHN JANSON |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | MATTHEW MAHLEBASHIAN |
| Construction near power lines | Cleared | 2/21/2023 | WALTER RAMIREZ |
| Stormwater Pollution Mitigatn | Cleared | 3/1/2023 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2023 | MATTHEW MAHLEBASHIAN |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | MATTHEW MAHLEBASHIAN |
| Sewer availability | Cleared | 3/3/2023 | MATTHEW MAHLEBASHIAN |
Contact Information
| Contractor | S M Development Company Inc; Lic. No.: 450270-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 3/31/2023 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | DAVID SCANTLIN |
| Special/Order Compliance | 4/17/2023 | Partial Inspection | MORRIS JACKSON |
| Deputy Wood Construction | 5/10/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/12/2023 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/12/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/12/2023 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 5/12/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/18/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 5/18/2023 | Partial Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/23/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/23/2023 | Approved | JOHN KIDWELL |
| Sewer | 6/6/2023 | Approved | JOHN KIDWELL |
| Underground Mechanical | 6/6/2023 | Approved | JOHN KIDWELL |
| Insulation | 6/21/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/21/2023 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 7/5/2023 | Approved | JOHN KIDWELL |
| Final | 9/5/2023 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/5/2023 | Approved | JOHN KIDWELL |
| Green Building Final | 9/5/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 9/5/2023 | Approved | JOHN KIDWELL |
| Final | 10/2/2023 | OK to Issue CofO | DAVID SCANTLIN |