15435 W VICTORY BLVD WEST 91406
Certificate Information: 15435 W VICTORY BLVD WEST 91406
- Application / Permit
- 22010-20000-03177
- Plan Check / Job No.
- B22VN09905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLan (n) 2-story det ADU per LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | KELVIN CHUONG |
| Corrections Issued | 7/25/2022 | KELVIN CHUONG |
| Quality Review Completed | 8/2/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/12/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/28/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/13/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/25/2023 | KELVIN CHUONG |
| Plan Check Approved | 1/27/2023 | KELVIN CHUONG |
| Issued | 1/31/2023 | APPLICANT |
| CofO in Progress | 11/7/2023 | RYAN SALAZAR |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
| CofO Issued | 1/10/2024 | RUBEN SALAS |
| Permit Finaled | 1/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2022 | MEGAN GODINEZ |
| ZI | Cleared | 7/26/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/27/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 9/29/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/2/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
| Engineer | Wassef,, Mena; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/9/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Pre-Inspection | 2/9/2023 | Partial Inspection | RYAN SALAZAR |
| Sewer | 2/9/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Underground Mechanical | 2/9/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 2/16/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 2/16/2023 | Not Ready for Inspection | JON MCHUGH |
| Sewer | 2/16/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Approval | RYAN SALAZAR |
| Sewer | 3/29/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Approval | RYAN SALAZAR |
| Gas Test | 5/22/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/22/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/6/2023 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/6/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/6/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 7/6/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/6/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 7/6/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 7/6/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 7/28/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/28/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 7/28/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/9/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 9/15/2023 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 9/25/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | RYAN SALAZAR |
| Final | 10/27/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 10/27/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 10/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 10/27/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/27/2023 | Approved | RYAN SALAZAR |
| Final | 11/6/2023 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 11/6/2023 | Approved | RYAN SALAZAR |