15435 W VICTORY BLVD WEST 91406

Certificate Information: 15435 W VICTORY BLVD WEST 91406

Application / Permit
22010-20000-03177
Plan Check / Job No.
B22VN09905
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLan (n) 2-story det ADU per LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 1/31/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 KELVIN CHUONG
Corrections Issued 7/25/2022 KELVIN CHUONG
Quality Review Completed 8/2/2022 RODOLFO ARIAS
Applicant returned to address corrections 12/12/2022 KELVIN CHUONG
Applicant returned to address corrections 12/28/2022 KELVIN CHUONG
Applicant returned to address corrections 1/13/2023 KELVIN CHUONG
Applicant returned to address corrections 1/25/2023 KELVIN CHUONG
Plan Check Approved 1/27/2023 KELVIN CHUONG
Issued 1/31/2023 APPLICANT
CofO in Progress 11/7/2023 RYAN SALAZAR
Permit Finaled 1/10/2024 RUBEN SALAS
CofO Issued 1/10/2024 RUBEN SALAS
Permit Finaled 1/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/26/2022 MEGAN GODINEZ
ZI Cleared 7/26/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 7/27/2022 MEGAN GODINEZ
Sewer availability Cleared 7/27/2022 MEGAN GODINEZ
Low Impact Development Cleared 9/29/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/29/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/2/2022 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352
Engineer Wassef,, Mena; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2023 Not Ready for Inspection RYAN SALAZAR
Footing/Foundation/Slab 2/9/2023 Not Ready for Inspection RYAN SALAZAR
Pre-Inspection 2/9/2023 Partial Inspection RYAN SALAZAR
Sewer 2/9/2023 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 2/9/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved JON MCHUGH
Footing/Foundation/Slab 2/16/2023 Approved JON MCHUGH
PLUMBING-Rough 2/16/2023 Not Ready for Inspection JON MCHUGH
Sewer 2/16/2023 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval RYAN SALAZAR
Sewer 3/29/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Partial Approval RYAN SALAZAR
Gas Test 5/22/2023 Approved RYAN SALAZAR
PLUMBING-Rough 5/22/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/6/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 7/6/2023 Approved RYAN SALAZAR
Green Building Rough 7/6/2023 Approved RYAN SALAZAR
HVAC-Rough 7/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/6/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 7/6/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 7/6/2023 Not Ready for Inspection RYAN SALAZAR
Insulation 7/28/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/28/2023 Approved RYAN SALAZAR
Shower Pan 7/28/2023 Approved RYAN SALAZAR
Drywall Nailing 8/9/2023 Approved RYAN SALAZAR
HVAC-Final 9/15/2023 Corrections Issued RYAN SALAZAR
HVAC-Final 9/25/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/27/2023 Approved RYAN SALAZAR
Final 10/27/2023 Corrections Issued RYAN SALAZAR
Green Building Final 10/27/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 10/27/2023 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 10/27/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 10/27/2023 Approved RYAN SALAZAR
Final 11/6/2023 OK to Issue CofO RYAN SALAZAR
Service/Power Release 11/6/2023 Approved RYAN SALAZAR