7524 N WHITAKER AVE 91406
Certificate Information: 7524 N WHITAKER AVE 91406
- Application / Permit
- 22010-20000-03168
- Plan Check / Job No.
- B22VN09901
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLan New Detached ADU 25'-3" x 33'-9" ADU CHECKED PER LAMC 12.22 A.33(C) AND (D)
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | SUNMIN LEE |
| Corrections Issued | 7/16/2022 | SUNMIN LEE |
| Quality Review Completed | 8/3/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/17/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 3/14/2023 | SUNMIN LEE |
| Plan Check Approved | 4/11/2023 | SUNMIN LEE |
| Issued | 4/18/2023 | APPLICANT |
| CofO in Progress | 5/7/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2022 | MEGAN GODINEZ |
| Watercourse | Cleared | 8/10/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 10/27/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/13/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fernandez,, Agapito B; Lic. No.: C56546 | 7400 E SLAUSON AVE STE S COMMERCE, CA 90040 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 5/16/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/23/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/23/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/23/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/23/2023 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/23/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/5/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 6/5/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/5/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/5/2023 | Approved | RAUL OLAGI |
| Sewer | 6/5/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 6/5/2023 | Partial Approval | RAUL OLAGI |
| Insulation | 6/13/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 6/23/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/23/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| FLOOD-Proofing Certificate | 9/17/2024 | Approved | RAUL OLAGI |
| Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 9/17/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/29/2025 | Approved | SALVADOR MARTINEZ |
| Final | 4/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 4/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 4/29/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Gas Test | 5/1/2025 | Approved | MICHAEL CORTEZ |
| HVAC-Final | 5/1/2025 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | SALVADOR MARTINEZ |
| Final | 5/6/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 5/6/2025 | Approved | SALVADOR MARTINEZ |