14827 W DEARBORN ST 91402
Certificate Information: 14827 W DEARBORN ST 91402
- Application / Permit
- 22010-20000-03146
- Plan Check / Job No.
- B22VN09866
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 43'-11" X 18' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/21/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | SELLA BENYAMIN |
| Corrections Issued | 7/12/2022 | SELLA BENYAMIN |
| Quality Review Completed | 7/14/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Plan Check Approved | 8/23/2022 | SELLA BENYAMIN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 5/21/2026 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/18/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/23/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/18/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/11/2023 | No Access for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/18/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/17/2024 | Conditional Approval | JOHN COLEMAN |
| Special/Order Compliance | 1/18/2024 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 1/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 2/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/8/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 3/8/2024 | Partial Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | JOHN COLEMAN |
| Insulation | 3/18/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 3/26/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 7/11/2024 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/31/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/11/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 10/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 10/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 10/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 10/28/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 11/1/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/1/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/6/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 1/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 10/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 10/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| Final | 1/8/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 1/8/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Service/Power Release | 1/8/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Final | 4/9/2026 | Approved | RAUL OLAGI |
| PLUMBING-Final | 4/9/2026 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 4/9/2026 | Partial Approval | RAUL OLAGI |
| Final | 4/17/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 4/17/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/20/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/20/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 5/20/2026 | Approved | JENNIFER RABUCHIN |