23052 W VANOWEN ST 91307

Certificate Information: 23052 W VANOWEN ST 91307

Application / Permit
22010-20000-03142
Plan Check / Job No.
B22VN09818
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR 27'10" x 37'-5" (881 SQ. FT.) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). DESIGN PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 8/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/28/2022 LUIS RINCON
Corrections Issued 6/29/2022 LUIS RINCON
Building Plans Picked Up 6/30/2022 APPLICANT
Plan Check Approved 8/23/2022 YAQUB MIRZA
Issued 8/23/2022 APPLICANT
CofO in Progress 6/13/2025 TROY SANDERS
Permit Finaled 7/18/2025 DANIEL ORRANTE
CofO Issued 7/18/2025 DANIEL ORRANTE
Permit Finaled 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/5/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/5/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/6/2022 CARLOS AGUILERA
Sewer availability Cleared 7/8/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2023 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved TROY SANDERS
Footing/Foundation/Slab 6/1/2023 Approved TROY SANDERS
ELECTRICAL-Rough 7/7/2023 Approved HORACE FULTZ
PLUMBING-Rough 7/7/2023 Approved HORACE FULTZ
Wood Frame 7/7/2023 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Approved MORRIS JACKSON
HVAC-Rough 7/28/2023 Approved MORRIS JACKSON
Rough-Elec/Plmb/HVAC 7/28/2023 Approved MORRIS JACKSON
Wood Frame 7/28/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/1/2023 Not Ready for Inspection MORRIS JACKSON
Insulation 8/1/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/16/2023 Approved TROY SANDERS
Green Building Rough 8/16/2023 Approved TROY SANDERS
Insulation 8/16/2023 Approved TROY SANDERS
Sewer 8/16/2023 Approved TROY SANDERS
Underground Mechanical 8/16/2023 Approved TROY SANDERS
Verify Sprinkler Sign Off 8/16/2023 Approved TROY SANDERS
ELECTRICAL-Final 8/12/2024 Not Ready for Inspection TROY SANDERS
Service/Power Release 8/12/2024 Approved TROY SANDERS
Green Building Final 1/7/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Not Ready GEVORK IPCHYAN
Gas Test 2/13/2025 Approved TROY SANDERS
HVAC-Final 2/13/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved TROY SANDERS
Smoke Detectors 2/13/2025 Approved TROY SANDERS
Drywall Nailing 6/13/2025 Approved TROY SANDERS
Final 6/13/2025 OK to Issue CofO TROY SANDERS
Green Building Final 6/13/2025 Approved TROY SANDERS